161206

From Cryowiki
Revision as of 13:36, 6 December 2016 by Mwright (talk | contribs) (→‎Piping)
Jump to navigationJump to search

Attendance

Mat, Shirley, Kelly, Rusty, Michele

Asked But Did Not Attend: Jonathan

Running Kinney Pump Piping outside CTF

3 options for running piping outside:

1. Between Gas tanks and building.

2. Running the piping on top of building

3. Running piping through the building


How the charge Codes are used

From Email Rusty sent on Dec 2nd:

conceptual planning (FMRIGO) The effort up to a conceptual design; which is 35%

Design and materials (FMECEU) The effort from 35% design to 100% (procurement documents)

or

We would like to be able to purchase main components after the 35%.

These components are on the "Valve - List"

Review set for Dec 8, 2016

35% is done after the:

1. Process diagram is done

2. Valve is list is approved

3. Installation sequence is approved.


Most of conceptional design done to prove that job can be done with minimal effect to operations.

The estimates did not include "work already done"

Utility Tree (Pipe support)

The only piping we would expect to be on the outside pipe support is for the 12" Kinney Pump suction header.

The other piping and conduits should all be routed inside

Water piping will all be done by the cryo group.

Action Items

Rusty needs the break up between techs and designers

Send Rusty and Michele the 3 options (3D models) for Kinney piping