Meeting Jan 30, 2016

From Cryowiki
Revision as of 14:55, 30 January 2017 by Creel (talk | contribs) (Created page with " == Attendance == Creel, Scanlon, Oren, Dixon == Agenda and Notes == '''1. Manpower ''' The EE has increased his hours on LCLS2. The ECAD designer is keeping up with L...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigationJump to search


Attendance

Creel, Scanlon, Oren, Dixon


Agenda and Notes

1. Manpower

The EE has increased his hours on LCLS2.

The ECAD designer is keeping up with LCLS2 needs.

Floyd Martin stated working in 87 on warm piping and will be starting on the 2K cold box this week.


2. Project

The next 2K cold box review will be the 90% sometime in January.

LN2 dewar might go out on the street soon.

Controls design review in early January 17. Scanlon says requirements keep changing. It was a procurement readiness review but now they are asking for ICD's FRS's etc.

Opinions differed wildly on the results of the 4K cold box review. One side indicates they did not meet the charge questions but the other indicated success in getting contractor to reconsider and adjust the schedules.

Ancillary equipment specs at SLAC for signatures.

Internal 2K piping is being worked with Hung yu and Damon Rath.


Action Items

1. Discuss LCLS2 budget delays impact on procurements and contract labor

2. Scanlon will check EECAD designers holiday plans.

Tim McCools leave schedule for the holidays is Dec. 23rd and 30th. And Jan. 2017 2nd-6th.

3. Rao indicated to Vishy that their might be an issue with the 2K configuration. Dana will discuss this with Vishy.

4. There is a meeting Friday to discuss if the conflat flanges can be used in the 2K system.