04/27/2017 Meeting
Attendance
Thompson, Creel, Dixon, Oren, Michalski, Arenius
Agenda and Notes
1. Operations
LINAC
Both LINACS at 4K
CHL1
We are managing inventory to position ourselves to start the warm up of the SC1.
CHL2
Has been shutdown and plant is being positioned for C6 work and electrical panel maintenance to be starter Monday. Our ETechs will also perform maintenance on our equipment during this time.
ESR
All of the Hall magnets are cold except one. We were able to get all the magnets cold with out the xferline but with the lead flows off.
CTF
The CTF UIM work is complete. We are working to restart the plant at this time. We fully expect to find and correct control system issues along the way.
HDR
Normal.
2. Projects
UIM
The CTF shutdown is complete. We fully expect to find and correct control system issues along the way. The 3" Linde ball valve does not seal so we are going to blank it off and restart the plant. A plan to fix the valve will be planned and coordinated.
UITF
Thermosiphon is being installed. There is a significant amount of controls work left to be done before this system can be made operational. We will likely start the controls work after the C6 installation.
MSU
We sent a compressor alignment package to Fabio. Mark Stapleton is at MSU for a 1 week trip to help them.
LCLS2
Recovery compressors on track for July. Still have not seen drawings for water skid. Dana gave a re-plan to LCLS2 project management.
3. Manpower
4. Info from Will
1. New director started Apr 3.
2. They have pushed the ESR2 money to at least 2018 and the replacement for SC1 might be put on the list ahead.
3. Nusair studying SC1 4-stage operation.
5. We are moving forward on engineering and design for SC1 (and ESR2)
5. Other
Action Items
1.
2.
Action Item Updates
1.
2.