05/02/2017 Meeting
Attendance
Thompson, Creel, ,Radovic, Dixon, Wright, Butler, Radovic, Wijeratne, Norton, Saringer, Schleeper, Yang, Perry, Laverdure
Goals
The purpose of this weekly meeting is to discuss plant operations and group projects with the cryogenics group managers and supervisors. During this meeting we will discuss ongoing and future projects, priorities, manpower, schedules, expenditures, and problems.
Agenda and Notes
1. Safety
We had an incident where an individual was working in the SBR compressor room and tripped over installed piping and injured his leg. His injury required stitches and is a recordable event.
2. Schedule
Near term schedule Media:img_3327.jpg
3. Operations (A brief description of the highlights for the past week at CHL's, ESR, HDR, CTF)
CTF is operating. Team is working on reassembling the K2.
ESR normal.
CHL1 at 4K
CHL2 is off to support C6 work.
CHL Recovery: Purifier 5 carbon has been replaced. pump and backfills on-going. After purifier 5 is online and operating acceptably, carbon will be replaced in bed #4.
HDR Normal
4. JLAB Internal Group Projects
CHL1 SC1 CC5
Final utubes for disconnecting SC1 are to be done Wed and Thur.
Air Liquide is expecting to have technician here on site first or second week of May.
Decisions need to be made regarding the flanging/sealing of the CC.
UIM (Wijeratne, Wright, Creel)
Calendar
The shutdown is scheduled from 17 Feb - 9 Apr (Dewar Full). We are in clean up mode anticipating restart around Thursday..