Alicia Saringer work items
From Cryowiki
Jump to navigationJump to search--Spreadsheets for CTF and new graphs. --CTF Inventory Calculation Development --P&I for Nate on removing and installing the junction box relief valves --Drawings for review LL sensor, relief valve set drawings, compressor relief valve dwg. --CHL2 RVs --EV development --CTF Dewar and Main Compressor Relief Valves.
--Looking into reducing/mitigating cavitation in the Kinney Pump system to try and bring down the suction line pressure.
--Working on changing the next three relief valves, RV2450, RV243SU and RV243RT.
--Add documents to docushare and recreate PS-7 for C9 Header
--Kinney Water Line Leak-Will be addressed during relocation. By-pass line leakage
--CTF Recovery Compressor C4 and C6 P&I
--Install the C.V. on C9
--Pressure Systems Part 9 review and comments to K. Dixon -Done --Flexitallic Flange torque requirements -Done
--Develop Milestone/schedule -Done
-Someone to cut Kinney Sight glass. -Done
--FlowSafe Dwgs per selected based on calculation. -Done
--Sightglass for the RV on compressors -Done
--KelF ring for EV245RT/DWG Dimensions. -Done
--Addressing EV245RT Leak. Currently working on repair. -Done
--Sight Glass Assembly Installation at Kinney Pump - -Done
--Relief Valve Instrumentation/Protected Zones (CTF Complete)
--Id. all RV Category on spreadsheet completed. Proceed to inspect then in accordance with the IC and get all ASME relief valves in the plant.
--Id relief valves on CHL2
--Liquid Level Indicator determined to go on the coalescer. Develop a drawing and plan. Waiting for the drawings to be completed. The John C Ernst soft parts are on order.
--CHL Recovery Compressor Header Redesign --Develop CTF Document - Ongoing
--CTF Spreadsheets - Ongoing - Get with Bill about full startup after power outage
--CTF Warm-Up/Cool Down (Complete-Review Thilan's plan)-Complete
--Recovery Compressor LOTO Review (Complete)-Second Review Complete
--Dunham-Bush Check Valve Hinge Installation Verification (Complete)
--Recovery Compressor Pipe Analysis (Complete) --LCLS II Spreader Analysis (Complete), Start White Paper (Complete), Comment Adjudication (Complete), Incorporate Comments and Develop Final Draft(Complete)-Revise to incorporate different lifting mechanisms --(Complete) --Bolting "Procedure" - complete --Shaft Seal on Kinney for M. Wright - complete