05/16/2017 Meeting
Attendance
Thompson, Creel, Radovic, Dixon, Butler, Radovic, Wijeratne, Norton, Saringer, Schleeper, Yang, Perry,
Laverdure on vacation
Goals
The purpose of this weekly meeting is to discuss plant operations and group projects with the cryogenics group managers and supervisors. During this meeting we will discuss ongoing and future projects, priorities, manpower, schedules, expenditures, and problems.
Agenda and Notes
1. Safety
No issues.
2. Schedule
Near term schedule Media:img_3327.jpg
3. JLAB Internal Group Projects
UIM (Wijeratne, Wright, Creel)
Cold box #3 Linde has returned to begin working through start up and cooldown sequences and move into acceptance testing next week. Double check what support might be needed for the weekend.
GPP (Yang, Thilan)
Kinney Pump Relocation
- Detailed design of Kinney suction and discharge piping system was completed.
- The material for Kinney suction has been received. The material for Kinney discharge has ordered.
- Started the detailed design package of the cooling water system.
- The actual design hours have been over the budget. This is mainly because:
1. The modification of the existing Coalescers piping system was not initially budgeted. 2. More efforts were put on the design in order to meet the clearness requirement of the control panel. 3. The girder and other components near the piping system had to be modeled after interference between the piping and structure components were found. 4. The design of the piping support was much more than originally estimated.
Gas Management System
- 35% concept planning has been completed.
- The 3D model was done based on the concept design.
- All pneumatic control valves have been ordered.
Check on parts ordering. Valves, transducers, venturies
CHL2 C6 (Perry, Creel)
C6 installation work has started. Mechanics are working now. Electrical work is complete. We are expecting about 2 more weeks of work to complete installation then commissioning will start. Code is loaded. Controls check out started. We will perform main motor bump and magnetic centering Thursday. Still on track for PHPK visit.
JLAB Guard Vac (Schleeper, Radovic)
Electrical techs are completing the power and controls work. Mechanical will then modify the railings.
CHL LN2 Dewar Fill Transfer line (Schleeper)
-process improvements being tested -vacuum needs to be pumped -relief valve needs to be replaced/ordered (will set up a meeting)
JLAB recovery header rework (Saringer, Nate)
Job is being re-planned to shrink the required down time and cost.
JLAB Vaporizer (Perry)
We have most of the parts. The installation is on hold. It might be used as a filler job if things ever get light. Robert will check if there is any instrumentation and controls associated. Not this year.
CHL to FEL Utubes (Perry, Corey)
If a designer becomes available they will be placed on this project. It is currently in Craig's queue.
CHL LN2 Dewar Instrumentation Replacement (Schleeper, Thompson) causing errors in the pressure gauge on fill station.
CHL LN2 Pressure Building Coil leaks (Schleeper, Thompson, Hunewill)
ESR Carbon Replacement (Schleeper, Butler)
Evaluate changing the carbon during the summer shutdown 2018.
ESR Oil Containment (Schleeper, Thompson), working. Paused to support C6 work.
CHL1 Regeneration Skid Removal (Schleeper, Thompson)
4. JLAB External Group Projects
Hall B 12GeV (Thompson)
We have been tasked with fabricating flex lines for the solenoid can. It will take approximately 4 months. (Jay). Roland is continuing to work with Ruben on solenoid can instrumentation as needed.
Solenoid is expected 12 May ????. Scott says officially its June.
UITF (Perry, Radovic)
Thermosiphon being installed. Utubes are being fabricated. The electrical controls work will start after guard vacuum.
CHL2 Main Compressor Oil Level Alarms (Saringer, Wright)
We are having trouble managing compressor oil levels especially when there are large ambient temperature changes. We need to work on a solution. Drawings are approved. We will start ordering parts soon.
NL cooldown header re-connection (Schleeper, Wright)
-NL piping has been purged with GN2, and pumped/backfilled (20mTorr). cool down flange has been re-connected and relief valve installed. -cool down valve has been tagged to contact creel or dixon prior to use. -long term plan is being developed.
Sintered Metal filter test:
-skid has been fabricated. Testing set to begin ????
SRF is planning to replace cold windows on 15 modules
Ongoing.
5. JLAB External Projects
LCLS2 (Dixon)
We are building two recovery compressors. Due in July 17'. (Issac) We are building a guard vac skid for LCLS2. Not started. Due end of October 17'(Issac). We might also fabricate a water skid. FDR for 2K cold box Mar 9. Issac and Stapleton found grit or metal shavings in the inlet piping of the compressor. Bill Crahen is investigating.
We are starting to buy hardware to build 230 bayonets in approximately 6-7 months.
Shop is starting to cut metal for the vacuum skid.
CTF CMTF Junction Box
Repair of EV245RT Coming up with preliminary design for applying force without an EV.
CHL
Inspection of Relief Devices per Pressure System's Requirement: Started CTF and CHL2. Meeting yesterday to decide path forward. Alicia is writing several task hazard analysis, CTList, TOSP.
6. Summer Maintenance Work Plan (All)
PRIORITY
CHL1 and CHL2 electrical maintenance including controls
GPP CTF gas management skid and Kinney piping move (engineering/design $$, parts $$$, labor $$$)
CHL1 regen skid disconnect (engineering/design 0, parts 0, labor $)
Add e-stop guards on all systems (engineering/design $, parts $, labor $)
SC1 Vacuum Controls (engineering/design 0, parts 0, labor $)
CHL1 C3 - Load Valve Readback and Power-meter (engineering/design ?, parts ?, labor ?) - Can be done anytime
CHL1 C6 - Load Valve Readback Calibration (engineering/design 0, parts 0, labor $) - Can be done anytime
CHL2 MCS2 Retighten Flexitalic Gaskets per torque spec. (engineering/design 0, parts 0, labor $)
CHL Hurricane Relief System - EV for SLinac not functional (engineering/design ?, parts ?, labor ?)
POSSIBLE
CHL1 MCB CAMAC to PLC conversion (engineering/design $, parts $, labor $$$)
CHL1 MCB1 Vacuum - Controls and Equipment (engineering/design $, parts $$$, labor $)
NOT POSSIBLE
CHL2 SC2 cold compressor power feedthru replacement (engineering/design 0, parts 0, labor $$)
CHL1 vaporizer cold piping (engineering/design 0, parts 0, labor $$$)
Spare utubes for c50 and c100 (engineering/design 0, parts $$, labor $$)
CHL/FEL shield utube (engineering/design $, parts $, labor $)
CHL Purifier LN2 Solenoid Replacement (engineering/design 0, parts $, labor $) - Can be done anytime
CHL1 MCB1 - MCS1 Rusty Flange, Bolt Change-out (engineering/design 0, parts 0, labor $)
SBR CBX Isolation (engineering/design $, parts $, labor $$??)
SBR C1/C2 - Install Current Transducer (engineering/design ?, parts ?, labor ?)
SBR C1 - Loading itself (engineering/design ?, parts ?, labor ?) - Can be done anytime
ESR-TL (EV11139) Valve Re-build (engineering/design 0, parts $, labor $)
CHL Recovery 10DR Valve - dismantle, header inspection (engineering/design 0, parts $/2, labor $)
CHL2 SCW Solenoid with Spools ((engineering/design $, parts $, labor $) - SV Ordered Already
CHL2 GN2 Vent Piping (engineering/design 0, parts 0, labor $)
CHL2 UCBX/LCBX backup vacuum - connect to K100 vacuum skid (engineering/design $, parts $, labor $)
CHL2 MCS2 - Replace valve on Purifier Discharge Header (engineering/design $, parts $, labor $) - Valve already bought.
7. Long Range Plans (Wright, Creel)
Jobs we are considering in no particular order
ESR gas management carbon bed maintenance (engineering/design $, parts $, labor $$)
ESR CAMAC to PLC conversion (engineering/design $$$, parts $$$, labor $$$)
? Action Items
1.
2. Before next meeting the persons whose name appears beside an item will write a short update.
3. Complete summer maintenance list
4. Need to start thinking about a new 2K cold box design using FRIB/LCLS2 cold compressor designs.
5. Need to start pushing the engineering/design effort forward for the ESR2 plant.
Action Item Updates
1.