JLab

Organize cryo pressure systems

  • CHL:
  # Replacement/upgrade of LN2 fill station gauging:
    -Materials: On-site
    -Pressure System:  Standard Maintenance
    -Drawings: N/A
    -Fabrication:  N/A
    -Operations:  Working.  Tank 2 complete.
    -Testing:  Snoop upon installation.
  # CHL Guard Vacuum
    -Materials:  Need to order three blind flanges (32 finish, 2 NPS)
    -Pressure System:  Signed
    -Drawings: Complete
    -Fabrication: N/A
    -Operations: N/A
    -Testing:  To be initial service leak checked upon completion of electrical work.
  # LN2 Dewar #1 instrumentation tubing replacement
    -Materials:  On order
    -Pressure System:  Held in DA review, pending drawing revision (to new PS requirements)
    -Drawings: 75600-0812 in revision
    -Fabrication: pending material/dpf
    -Operations: N/A
    -Testing:  To be initial service leak checked upon completion.


  # LN2 PBC leaks
    -Materials:  TBD
    -Pressure System:  TBD
    -Drawings: TBD
    -Fabrication: TBD
    -Operations: All leaks have been identified and need to be tabulated and planned for repair/replacement. 
    -Testing:  TBD


  # CHL Recovery Purifier Sieve replacement
    -Materials:  on-site
    -Pressure System:  N/A
    -Drawings: N/A
    -Fabrication: N/A
    -Operations: Needs to be scheduled/planned. 
    -Testing:  N/A


  # ESR ORS Carbon Replacement
    -Materials:  Need to be identified and ordered.
    -Pressure System:  N/A
    -Drawings: Need to be developed.
    -Fabrication: awaiting drawings
    -Operations: Needs to be scheduled/planned. 
    -Testing:  Snoop at joints.  Spool pieces will need to be tested.
  # ESR 15K U-tube
    -Materials:  Being ordered
    -Pressure System:  in review
    -Drawings: issued.
    -Fabrication: awaiting materials
    -Operations: U-tube will be stabbed at earliest convenience
    -Testing:  pressure test per DPF
  # ESR Oil collection
    -Materials:  TBD
    -Pressure System:  TBD
    -Drawings: TBD
    -Fabrication: TBD
    -Operations: May require piping removal or plant shutdown
    -Testing:  not likely. category D piping at most.


ESR Status

-Halls A and C are cold and on cold return. -Hall C has been performing heat leak testing of the SHMS Q2. Expected to carry into week of 1/22. -Hall B is cooling solenoid. Expected to be on cold return 1/20/2017. -Hall C target system is being cleaned. Not connected to ESR or recovery as of now. -CHL-ESR x-fer line will be in use occasionally over the next week.


MSU FRIB

Organize and publish pressure system documentation for pressure systems. Actions are as listed in the summary document.