02/07/2017 Coordination Meeting

From Cryowiki
Jump to navigationJump to search

Attendance

Creel, Wright, Schleeper, Fair, Kashy, Bridza, Lassiter, Kepple, Fansler, Gomez, Oren

Agenda and Notes

This meeting is to discuss the ESR capacity usage by the Halls.


1. ESR History

Plant originally built in 1978 for the LBL ESCAR Project. It operated < 900 hours before being shutdown.

Plant was moved to JLAB and installed in 1994 JLAB to support Hall's A, B, and C. The plant has been in nearly continuous operation for 22 years.


2. ESR Capacity

Plant capacity envelope (1500W at 4.5K) OR (800W at 4.5K PLUS 1200W at 15K)

Additional transient capacity available from CHL via transferline of up to 20g/s at 4.5K


3. Recent History


4. Plan Forward

Action Items

1. Finish the ESR2 design, fabrication, and commissioning ... quickly.