David Schleeper work items

From Cryowiki
Revision as of 08:59, 16 February 2017 by Davids (talk | contribs) (→‎JLab)
Jump to navigationJump to search

JLab

2/16 Update Organize cryo pressure systems

  • CHL:
  1 Replacement/upgrade of LN2 fill station gauging:
    -Materials: On-site
    -Pressure System:  Standard Maintenance
    -Drawings: N/A
    -Fabrication:  N/A
    -Operations:  Assigned Tank 2 complete.  Tank 1 is being prioritized.
    -Testing:  Snoop upon installation.
  2 CHL Guard Vacuum
    -Materials:  installed
    -Pressure System:  Signed
    -Drawings: Complete
    -Fabrication: N/A
    -Operations: Will test run upon completion of electrical and IA installation.
    -Testing:  To be initial service leak checked upon completion of electrical work.  Pump temperatures will also need to be monitored.
  3 LN2 Dewar #1 instrumentation tubing replacement
    -Materials:  On-site
    -Pressure System:  Signed
    -Drawings: Complete
    -Fabrication: All paperwork and materials are with Scott.  He is scheduling.
    -Operations: N/A
    -Testing:  To be initial service leak checked upon completion.  


  4 LN2 PBC leaks
    -Materials:  TBD
    -Pressure System:  TBD
    -Drawings: TBD
    -Fabrication: TBD
    -Operations: All leaks have been identified and tabulated.  Ops is investigating the repair of threaded connections.
    -Testing:  Snoop


  5 CHL Recovery Purifier Sieve replacement
    -Materials:  on-site
    -Pressure System:  N/A
    -Drawings: N/A
    -Fabrication: N/A
    -Operations: P5 sieve replaced and ready for use.
    -Testing:  N/A


  6 ESR ORS Carbon Replacement
    -Materials:  Lifting adapter approved by Sprouse.  Estimating ~$350 for materials
    -Pressure System:  N/A
    -Drawings: Need to be developed.
    -Fabrication: awaiting drawings
    -Operations: Needs to be scheduled/planned.  Probably next summer
    -Testing:  Spool pieces will need to be tested.
  7 ESR 15K U-tube
    -Materials:  ordered
    -Pressure System:  signed
    -Drawings: issued.
    -Fabrication: in fabrication (expect to test by 3/3/17)
    -Operations: U-tube will be stabbed at earliest convenience (when it will not impact target schedule)
    -Testing:  pressure test per DPF
  8 ESR Oil collection
    -Materials:  TBD
    -Pressure System:  TBD
    -Drawings: TBD
    -Fabrication: TBD
    -Operations: May require piping removal or plant shutdown
    -Testing:  not likely. category D piping at most.


  9 CHL IA modification
    -Materials:  ordered
    -Pressure System:  TBD
    -Drawings: in development
    -Fabrication: TBD
    -Operations: N/A
    -Testing:  Initial service leak test
  10 CHL purifier sieve heater
    -Materials:  Awaiting design
    -Pressure System:  Awaiting design
    -Drawings:  Awaiting basic design
    -Fabrication:  Awaiting drawings
    -Operations:  TBD
    -Testing: Test per B31.3, with consideration for temperature requirements.

ESR Status

  1. Halls A, B, and C are on cold return. Hall C magnets filling.
  2. Hall C is cooling SHMS Dipole to 100K. U-tubes were stabbed Tuesday.
  3. Hall C target system is being cleaned. Not connected to ESR or recovery as of now.
  4. CHL-ESR x-fer line will be in use occasionally over the next week.
  5. T2 will need to be stopped to facilitate simple trouble shooting on inlet valve/actuator.

MSU FRIB

Organize and publish pressure system documentation for pressure systems. Actions are as listed in the summary document.

  1. IA complete
  2. GV complete
  3. LND complete
  4. waiting for examination docs from embler.