New GV Skid Meetings

Attendance

Creel, Radovic, Dixon, Wright, Norton, Schleeper, Roland

Goals

Discussion about Guard Vac issues remaining


Agenda and Notes

Conduit rework - Put conduit above control enclosures.

Instrument Box size - Smaller box for terminals/PTs... - Leaving on left side of guard vac skid (with back to SBR MCC)

Limit Switch on the Inlet Solenoids - Yes.

Pressure Taps for reading pump pressure with valve closed. - Install pressure tap at suction of each guard vac pump so we can attach portable vac gauge. - Install DP Switch to prevent oil backflow, similar to SNS. - DP Switch to be wired into starter box (series w/ Inlet solenoid)

Panel for displaying pump pressures (digital readouts) - Not at this time ($ concerns)

Stack Lights for on/off display - Tentative No.

Location of linac guard vac gauge panel. - Remove gauge panel completely...

Removing handrail. - Will be done ASAP after Conduit is moved.

Securing the skid base to the floor - Bolt it to the floor and shim it.


Instrument air branch.

- In the process of drawings being made.

Action Items

1.


Action Item Updates

1.