(Created page with "* NPS design - info on detector front minimum distance from design studies * Budgetary quotes for PbWO4 and PMTs * Continue discussion of NPS project funding strategies, e.g., ...") |
|||
(One intermediate revision by the same user not shown) | |||
Line 1: | Line 1: | ||
+ | ITEMS FOR DISCUSSION: | ||
+ | |||
* NPS design - info on detector front minimum distance from design studies | * NPS design - info on detector front minimum distance from design studies | ||
Line 4: | Line 6: | ||
* Continue discussion of NPS project funding strategies, e.g., budget optimizations | * Continue discussion of NPS project funding strategies, e.g., budget optimizations | ||
+ | |||
+ | |||
+ | MATERIAL WE MAY USE DURING THE MEETING: | ||
+ | |||
+ | * [https://wiki.jlab.org/cuawiki/images/6/65/PbWO4_properties_summary.pdf Overview crystal requirements (PANDA/CMS/NPS) and comparison to LSO/LYSO] | ||
+ | |||
+ | * [https://wiki.jlab.org/cuawiki/images/b/b2/Analysis_PbWO4_properties_hamlet.pdf Analysis of PbWO4 properties and definition of NPS requirements (Hamlet)] | ||
+ | |||
+ | * Performance of PWO crystals from SICCAS in PANDA geometry - report by R. Novotny (see Carlos's email from 23 August 2013) | ||
+ | |||
+ | * Summary of quotations received so far |
Latest revision as of 11:36, 11 September 2013
ITEMS FOR DISCUSSION:
- NPS design - info on detector front minimum distance from design studies
- Budgetary quotes for PbWO4 and PMTs
- Continue discussion of NPS project funding strategies, e.g., budget optimizations
MATERIAL WE MAY USE DURING THE MEETING:
- Performance of PWO crystals from SICCAS in PANDA geometry - report by R. Novotny (see Carlos's email from 23 August 2013)
- Summary of quotations received so far