Timeline
- February - pre-installation tasks (see: link)
- complete calorimeter trigger
- upgrade HMS DAQ
- calorimeter tests
- March - pre-installation tasks (see: link)
- complete calorimeter trigger
- upgrade HMS DAQ
- calorimeter tests
- April 15 - April 30: start disconnecting cables from NPS in EEL108
- disconnect cables
- bundle cables and prepare for transport
- May 3rd: NPS detector moves to Hall C
- May 15 - May 30: connect cables to the NPS detector
- June 1 - July 14: NPS detector checkout in Hall C
- July 17: NPS Experiments Phase 1 start