Difference between revisions of "Overview: What is happening when for collaborators"
Jump to navigation
Jump to search
(Created page with "'''Timeline''' * February - pre-installation tasks (see: link) ::* complete calorimeter trigger ::* upgrade HMS DAQ ::* calorimeter tests * March - pre-installation tasks (s...") |
|||
Line 1: | Line 1: | ||
'''Timeline''' | '''Timeline''' | ||
− | * February - pre-installation tasks (see: link) | + | * '''February''' - pre-installation tasks (see: link) |
::* complete calorimeter trigger | ::* complete calorimeter trigger | ||
::* upgrade HMS DAQ | ::* upgrade HMS DAQ | ||
::* calorimeter tests | ::* calorimeter tests | ||
− | * March - pre-installation tasks (see: link) | + | * '''March''' - pre-installation tasks (see: link) |
::* complete calorimeter trigger | ::* complete calorimeter trigger | ||
::* upgrade HMS DAQ | ::* upgrade HMS DAQ | ||
::* calorimeter tests | ::* calorimeter tests | ||
− | * April 15 - April 30: start disconnecting cables from NPS in EEL108 | + | * '''April 15 - April 30''': start disconnecting cables from NPS in EEL108 |
::* disconnect cables | ::* disconnect cables | ||
::* bundle cables and prepare for transport | ::* bundle cables and prepare for transport | ||
− | * May 3rd: NPS detector moves to Hall C | + | * '''May 3rd''': NPS detector moves to Hall C |
− | * May 15 - May 30: connect cables to the NPS detector | + | * '''May 15 - May 30''': connect cables to the NPS detector |
− | * June 1 - July 14: NPS detector checkout in Hall C | + | * '''June 1 - July 14''': NPS detector checkout in Hall C |
− | * July 17: NPS Experiments Phase 1 start | + | * '''July 17''': NPS Experiments Phase 1 start |
Revision as of 09:58, 7 February 2023
Timeline
- February - pre-installation tasks (see: link)
- complete calorimeter trigger
- upgrade HMS DAQ
- calorimeter tests
- March - pre-installation tasks (see: link)
- complete calorimeter trigger
- upgrade HMS DAQ
- calorimeter tests
- April 15 - April 30: start disconnecting cables from NPS in EEL108
- disconnect cables
- bundle cables and prepare for transport
- May 3rd: NPS detector moves to Hall C
- May 15 - May 30: connect cables to the NPS detector
- June 1 - July 14: NPS detector checkout in Hall C
- July 17: NPS Experiments Phase 1 start