'''Timeline''' | '''Timeline''' | ||
− | * '''February''' - pre-installation tasks (see: link) | + | * '''February''' - pre-installation tasks (see: [https://docs.google.com/spreadsheets/d/1zvJLaskBxPr61IM0zkmumfyurz3CvkXzL0oiQSEl2Ss/edit#gid=1452894085 link]) |
::* complete calorimeter trigger | ::* complete calorimeter trigger | ||
::* upgrade HMS DAQ | ::* upgrade HMS DAQ | ||
::* calorimeter tests | ::* calorimeter tests | ||
− | * '''March''' - pre-installation tasks (see: link) | + | * '''March''' - pre-installation tasks (see: [https://docs.google.com/spreadsheets/d/1zvJLaskBxPr61IM0zkmumfyurz3CvkXzL0oiQSEl2Ss/edit#gid=1452894085 link]) |
::* complete calorimeter trigger | ::* complete calorimeter trigger | ||
::* upgrade HMS DAQ | ::* upgrade HMS DAQ |
Revision as of 14:52, 7 February 2023
Timeline
- February - pre-installation tasks (see: link)
- complete calorimeter trigger
- upgrade HMS DAQ
- calorimeter tests
- March - pre-installation tasks (see: link)
- complete calorimeter trigger
- upgrade HMS DAQ
- calorimeter tests
- April 15 - April 30: start disconnecting cables from NPS in EEL108
- disconnect cables
- bundle cables and prepare for transport
- May 3rd: NPS detector moves to Hall C
- May 15 - May 30: connect cables to the NPS detector
- June 1 - July 14: NPS detector checkout in Hall C
- July 17: NPS Experiments Phase 1 start