Difference between revisions of "Summary 2/3/20"
Jump to navigation
Jump to search
Line 162: | Line 162: | ||
'''NPS ASSEMBLY DISCUSSION''' (all) | '''NPS ASSEMBLY DISCUSSION''' (all) | ||
− | * | + | * Target date to start assembly is: October 2020 |
+ | ::* Frame is expected to arrive at JLab by beginning of September | ||
+ | |||
+ | * Discussion about pre-assembly preparations | ||
+ | ::* mu metal tubes will be assembled in Orsay | ||
+ | ::* PMT+divider assembly done at JLab | ||
+ | ::::* check if possible to install kapton tape around PMT to insulate it from the mu metal | ||
+ | ::* pre-shaping crystal wrapper - for FCAL use oven at 100 degC for 20 min and special tool | ||
+ | ::* how to monitor thickness increase of crystal dimension when adding tape to make it fit in the frame | ||
+ | ::* need space for assembly and storage of frame - prefer climate controlled | ||
+ | ::* need at least one fully instrumented crate to test out things before end of year | ||
+ | |||
+ | * Discussion about crystal stacking | ||
+ | ::* nominal: partial stacking - with outer two layers SICCAS (may change depending on communication with CRYTUR in May 2020 - see next point) | ||
+ | ::* Check with CRYTUR if production of remaining 250 crystals can be expedited with early FY21 procurement - ideally would like all crystals by June 2021 | ||
+ | |||
+ | * Discussion about coordination of resources for stacking | ||
+ | |||
+ | * DAQ testout - by end of the year full create with VTP | ||
+ | ::* readout seems straightforward | ||
+ | ::* cables | ||
+ | ::* computer, disk space | ||
+ | |||
+ | * HV Divider modification - decide by summer | ||
+ | ::* need time estimate for modification - need all modified dividers by end of year 2020 | ||
+ | ::* additional resources needed? | ||
+ | |||
+ | '''SIMULATIONS AND RECONSTRUCTION SOFTWARE''' (Ho San) | ||
+ | |||
+ | * Full NPS model with carbon frame implemented | ||
+ | ::* still to be done: latest on mu metal shielding | ||
+ | |||
+ | * Energy resolution: <1% constant term, dominated by electronics, noise | ||
+ | |||
+ | * Anode current estimate seems high | ||
+ | ::* check on a method to measure it | ||
+ | |||
+ | * Iron shielding around beam pipe | ||
+ | ::* not specifically needed for NPS - mainly to reduce fields around the beam line | ||
+ | |||
+ | * Reconstruction software is ready | ||
+ | |||
+ | * '''Action Items:''' | ||
+ | ::* Include mu metal shielding details in simulation | ||
+ | ::* Check impact of different fringe fields on physics | ||
+ | |||
+ | '''CALIBRATIONS''' (Jacob) | ||
+ | |||
+ | * Studied possible calibration with elastics and found a set of kinematics - need to optimize further | ||
+ | |||
+ | * '''Action Items''': | ||
+ | ::* Continue studies of calibration methods | ||
+ | ::::* Elastics: determine where the proton goes with electron fixed – can one place an additional small detector? | ||
+ | |||
+ | |||
+ | '''NPS EXPERIMENTS - TCS''' (Marie) | ||
+ | |||
+ | * Experiment getting ready to re-present to PAC to remove the condition for full approval | ||
+ | |||
+ | * Main question is still the proton detection - can the low momentum protons be measured after the high magnetic field? | ||
Latest revision as of 16:23, 7 February 2020
MECHANICAL DESIGN (Paulo, Steve L.)
- No significant changes in design since ERR
- Action item: steps towards assembly and commissioning:
- Check and document interference for all kinematics again including those for the DVCS experiment from Hall A
- dDocument time estimates for configuration changes, e.g. moving the NPS from one side to the other, rotating the magnet
- Identify and document items that can be done in advance of installation, e.g. welding the plates on the SHMS (requires finishing the drawings)
MAGNET (Charles)
- Magnet was energized to 25% (250A) of the max current
- Simulations have shown that for DVCS/pi0 it would be sufficient to energize the magnet to 2/3 of the max current - this allows to relax the requirements for a full current test. However, note that for RCS need the full field to deflect electrons
- Running at lower current also has an impact on the HMS optics design
- Action Items:
- Check measurements vs 3D calculations
- Make table of fringe fields vs. current and check simulations for physics impact
- Decide on what fraction of maximum current to run the magnet for first run group – will also impact HMS optics
DETECTOR FRAME OVERVIEW (Emmanuel)
- Final design
- support structure has been built
- new shielding design was adapted
- no change in cooling strategy
- PMT assembly concept ready (see a prototype here)
- attachment PMT-crystal through optical grease - some rotation is possible, note that it is important to check alignment from the front during installation
- HV and LEMO connectors on top of the box as before
- Parts manufacturing
- Large fraction has been received or is expected to arrive in mid-February; some delay in parts related to new shielding strategy, but still expect delivery of frame by August 2020
- Optical fibers: 28mm diameter quartz fiber
- Cut and polishing will be done in Orsay
- Carbon holders
- Infrastructure
- Temperature sensors (63 front + 63 side), PT 100 Ohm
- goal is to measure crystal temperature, no feedback, no interlock, but should be in alarm handler
- radiation concerns when operating in the hall
- Chiller - radiation concerns
- heat exchanger air flow - optimized, not much overall since many cables
- Action Items
- Finalize quotes, e.g. for quartz and mu metal
- Implement the new magnetic shielding design – includes ordering all parts (honeycomb, mu metal, iron shielding, aluminum plates, supports), assembly, and testing
- Send temperature control information to Brad to figure out readout (include in alarm handler, but no feedback, no interlock)
- Determine needs for operating chiller in Hall C, e.g. shielding, order spares
- Send crystal wrapping material for pre-shaping to JLab
- Check uniformity of fiber transmittance after cut/polish
- Test for LED system cross talk for adjacent PMTs
- Check if Kapton tape should be used around the PMT to insulate it from the mu metal cylinder
- Determine if there is a way to monitor thickness increase of crystals when adding tape
DETECTOR BOX (Laurent)
- Built and assembled
- Discussion about mounting holes to install the box on the JLab fixture (once installed, all lifting will be done from the JLab fixture)
- Action items:
- re-calculate center of gravity
- decide on how to attach NPS frame to JLab fixture - bolts, weld?
PCB, CABLES, ELECTRICAL (Thi)
- Interface bases, HV-LED - Fischer connectors
- HV cables (Samtec)
- tested wires in each cable to detect short circuits, bad connections
- tested HV on each cable
- Anode cables - waiting for LEMO connector, SMA side done
- Systec + LPC
- LED cables tested in similar way as HV cables
- developed special tool for these tests
CRYSTALS (Vladimir)
- Have been receiving crystals from CRYTUR and characterizing - 100% acceptance
- September 2020: expect to have ~630 crystals
- April 2021: expect to have 900 CRYTUR crystals
- rate of production is 30-40 crystals/month with PANDA or other production ongoing - most recently 30 pieces/month
- fastest production rate was 250 crystals/3 months
- slowest production rate is anticipated to be 15-20 crystals/month, e.g. with large PANDA order in parallel
- Have 460 SICCAS crystals on site
- 700 PMTs are on site
- Action items:
- Send 10 CRYTUR crystals and full-size glass to Orsay for irradiation tests
- Decide on final stacking configuration – current nominal configuration is two outer layers SICCAS, rest CRYTUR
- Check with CRYTUR if possible to expedite crystal production of outstanding 250 crystals with an early FY21 procurement
HV DIVIDERS (Fernando, Julie)
- All dividers are assembled at OU and awaiting decision on specifics of the modification
- Nonlinearity of bypassed amplifier is 1-2% depending on pre-amp gain (0.5, 1, 2 V to match fADC)
- gain 3: nonlinearity increases to ~4% (2 V) and ~11% (0.5V)
- Reasonably good linearity at gain 3 - still analyzing anode current
- Action items:
- Check on the method to measure anode current, e.g. in Hall C
- Further analyze existing anode current data from Hall D
- Decide on final HV divider gain
- Determine need for additional resources and/or funding beyond what was planned
DAQ, ELECTRONICS, HV (Brad)
- Support HW
- Patch panel, NPS-DAQ cabling design near completion
- HV crate procurement complete
- HV cables/connectors - some work needed here
- Initially recommended HV connectors are very expensive - alternative from CAEN might be a good solution
- Slow controls
- LED controls (starting point will be DIRC LED pulser) - DSG+FE, specs submitted and confirmed
- Integrated NPS controls based on ComCAL GUI - confirm/schedule with DSG
- Brad is point of contact for NPS slow controls
- DAQ HW Procurement - ongoing
- Computer hardware, network upgrade ongoing
- Single board computers (5+1)
- VTP boards (5+1)
- VXS crates (2/5 in hand, purchase 3)
- FADC250 available, but must reserve when dates for run known
- DAQ Firmware - requires new development
- request submitted and confirmed (FE group) - requires 3.5 person months
- Analyzer Hall C modifications
- decoding
- NPS specific
- Action Items:
- Complete procurements (computer hardware, VXS crates, modules, patch panel hardware)
- HV cabling/connectors: count available channels from, e.g. BigCAL (should be ~1700) and decide on type of connectors to procure
- Work with designers on cable runs and cable motion strategy
- Check with designers on roof block modification for feedthrough HV cabling
- Develop DAQ firmware (VTP, F250, TI/TM, CODA ROC driver) – FE/DAQ group
- Develop LED control system (HW interface, firmware+SW) – FE/DAQ group
- Confirm with DSG the development of slow control SW (start from Comcal GUI, HV, temp display, calo protection)
- Start Analyzer development (multi-block decoding, high level NPS class integration)
PATCH PANEL, CABLING, LCW (Joe)
- LCW and power supply available for currents ~800A - should be ok for NPS full power
- HV channels - feedthrough instead of patch panel
- need to check on roofblock electronics hut details - check with designers
NPS ASSEMBLY DISCUSSION (all)
- Target date to start assembly is: October 2020
- Frame is expected to arrive at JLab by beginning of September
- Discussion about pre-assembly preparations
- mu metal tubes will be assembled in Orsay
- PMT+divider assembly done at JLab
- check if possible to install kapton tape around PMT to insulate it from the mu metal
- pre-shaping crystal wrapper - for FCAL use oven at 100 degC for 20 min and special tool
- how to monitor thickness increase of crystal dimension when adding tape to make it fit in the frame
- need space for assembly and storage of frame - prefer climate controlled
- need at least one fully instrumented crate to test out things before end of year
- Discussion about crystal stacking
- nominal: partial stacking - with outer two layers SICCAS (may change depending on communication with CRYTUR in May 2020 - see next point)
- Check with CRYTUR if production of remaining 250 crystals can be expedited with early FY21 procurement - ideally would like all crystals by June 2021
- Discussion about coordination of resources for stacking
- DAQ testout - by end of the year full create with VTP
- readout seems straightforward
- cables
- computer, disk space
- HV Divider modification - decide by summer
- need time estimate for modification - need all modified dividers by end of year 2020
- additional resources needed?
SIMULATIONS AND RECONSTRUCTION SOFTWARE (Ho San)
- Full NPS model with carbon frame implemented
- still to be done: latest on mu metal shielding
- Energy resolution: <1% constant term, dominated by electronics, noise
- Anode current estimate seems high
- check on a method to measure it
- Iron shielding around beam pipe
- not specifically needed for NPS - mainly to reduce fields around the beam line
- Reconstruction software is ready
- Action Items:
- Include mu metal shielding details in simulation
- Check impact of different fringe fields on physics
CALIBRATIONS (Jacob)
- Studied possible calibration with elastics and found a set of kinematics - need to optimize further
- Action Items:
- Continue studies of calibration methods
- Elastics: determine where the proton goes with electron fixed – can one place an additional small detector?
NPS EXPERIMENTS - TCS (Marie)
- Experiment getting ready to re-present to PAC to remove the condition for full approval
- Main question is still the proton detection - can the low momentum protons be measured after the high magnetic field?
Additional Notes by Charles Hyde
- •Summarize full to-do list in hall, and estimated time to completion
- •Estimate time for configuration changes during beam running
- •Document interferences between NPS, BeamLine, HMS
- •Kinematic configurations are dynamic (addition of beam time from E12-06-114, uncertain beam energy in 2022)
- • How is the Calorimeter, Cabling, etc assembled
- •Do we run Sweep Magnet at full power or ~30%?
- •DVCS, pi0 maybe OK at 30% power
- •Future RCS will require full power (with NPS on outer side of SHMS)
- • Do we mix-and-match Crytur and SICCAS crystals?
- •Order ~200 more crystals from Crytur and wait ~1year for full delivery?