(Created page with "PARTICIPANTS: Aaron Brown, Bogdan Wojtsekjhowski, Hamlet Mkrtchyan, David Hamilton, Carlos Munoz-Camacho, Tanja Horn, Steven Lassiter, Rolf Ent, Ho San Ko, Paulo Medeiros, Var...") |
|||
Line 59: | Line 59: | ||
− | NEXT MEETING: THURSDAY 27 AUGUST AT 9:00AM (ET) | + | '''NEXT MEETING: THURSDAY 27 AUGUST AT 9:00AM (ET)''' |
Latest revision as of 12:31, 31 July 2020
PARTICIPANTS: Aaron Brown, Bogdan Wojtsekjhowski, Hamlet Mkrtchyan, David Hamilton, Carlos Munoz-Camacho, Tanja Horn, Steven Lassiter, Rolf Ent, Ho San Ko, Paulo Medeiros, Vardan Tadevosyan, Marie Boer, Vladimir Berdnikov, Brad Sawatzky, Petr Stepanov
FRAME (Carlos)
- Orsay Lab status back to normal
- Ongoing work: optical fibers tests
- defining length, polishing and cleaving procedures - easiest to cleave and no polish (polish scratches, impacts boundaries - see photo)
FAST ELECTRONICS GROUP UPDATE (Chris, Brad S.)
- Procurements of DAQ/readout related items: all in procurement except for HV cables
- HV cable discussion with DSG coming up - more detail next time
- Hall C network infrastructure in good shape
- planning to install a new 40GB switch during the next down
- Outstanding procurement items for NPS
- HV connectors
- model: go straight to hut, no benefit to go through path
- Samtec connectors HV rating - check with C. Cuevas
- Replace cdaql3 as primary file server
- DAQ fibers to SHMS
- Firmware and clustering code for crystal readout - people assigned to different projects, should start soon
MECHANICAL/DESIGN (Paulo, Steve L.)
- Target deck reinforcement out for review
- Magnet deck reinforcement plates - to be released in the next few months
- Power supply for magnet - need to further investigate if a suitable one is available
- have some candidates, e.g. Hall A
- Notes from Steve: main coil is ~1kA at 115Volts; corrector coils are 520A at 42V
DSG UPDATES (Aaron)
- Work ongoing
- Meeting with Brad about HV cables scheduled - will have more detail next time
NPS PROPOSALS
- Positron DVCS (Carlos)
- Reviews supportive of case
- Listing of items required to establish a positron beam
- Important to to have multi-hall operation for positrons
- Presentation will be on Wednesday - link to BJ available upon request (contact Carlos)
- TCS (Marie)
- Working on preparing a response to the reviewers - should be sent to both theory and experiment reviewers, plus Chair of the PAC and Chair of the User Board
- Good to include a description of overall trigger design in the slides
NEXT MEETING: THURSDAY 27 AUGUST AT 9:00AM (ET)