Difference between revisions of "Overview: What is happening when for collaborators"

From Cuawiki
Jump to navigation Jump to search
(Created page with "'''Timeline''' * February - pre-installation tasks (see: link) ::* complete calorimeter trigger ::* upgrade HMS DAQ ::* calorimeter tests * March - pre-installation tasks (s...")
 
 
(2 intermediate revisions by the same user not shown)
Line 1: Line 1:
 
'''Timeline'''
 
'''Timeline'''
  
* February - pre-installation tasks (see: link)
+
* '''February''' - pre-installation tasks (see: [https://docs.google.com/spreadsheets/d/1zvJLaskBxPr61IM0zkmumfyurz3CvkXzL0oiQSEl2Ss/edit#gid=1452894085 link])
 
::* complete calorimeter trigger
 
::* complete calorimeter trigger
 
::* upgrade HMS DAQ
 
::* upgrade HMS DAQ
 
::* calorimeter tests
 
::* calorimeter tests
  
* March - pre-installation tasks (see: link)
+
* '''March''' - pre-installation tasks (see: [https://docs.google.com/spreadsheets/d/1zvJLaskBxPr61IM0zkmumfyurz3CvkXzL0oiQSEl2Ss/edit#gid=1452894085 link])
 
::* complete calorimeter trigger
 
::* complete calorimeter trigger
 
::* upgrade HMS DAQ
 
::* upgrade HMS DAQ
 
::* calorimeter tests
 
::* calorimeter tests
  
* April 15 - April 30: start disconnecting cables from NPS in EEL108
+
* '''April 15 - April 30''': start disconnecting cables from NPS in EEL108
 
::* disconnect cables
 
::* disconnect cables
 
::* bundle cables and prepare for transport
 
::* bundle cables and prepare for transport
  
* May 3rd: NPS detector moves to Hall C
+
* '''May 3rd''': NPS detector moves to Hall C
  
* May 15 - May 30: connect cables to the NPS detector
+
* '''May 15 - May 30''': connect cables to the NPS detector ([https://docs.google.com/spreadsheets/d/1zvJLaskBxPr61IM0zkmumfyurz3CvkXzL0oiQSEl2Ss/edit#gid=0 installation tasks])
  
* June 1 - July 14: NPS detector checkout in Hall C
+
* '''June 1 - July 14''': NPS detector checkout in Hall C
  
* July 17: NPS Experiments Phase 1 start
+
* '''July 17''': NPS Experiments Phase 1 start

Latest revision as of 14:53, 7 February 2023

Timeline

  • February - pre-installation tasks (see: link)
  • complete calorimeter trigger
  • upgrade HMS DAQ
  • calorimeter tests
  • March - pre-installation tasks (see: link)
  • complete calorimeter trigger
  • upgrade HMS DAQ
  • calorimeter tests
  • April 15 - April 30: start disconnecting cables from NPS in EEL108
  • disconnect cables
  • bundle cables and prepare for transport
  • May 3rd: NPS detector moves to Hall C
  • June 1 - July 14: NPS detector checkout in Hall C
  • July 17: NPS Experiments Phase 1 start