Difference between revisions of "Summary 2/3/20"

From Cuawiki
Jump to navigation Jump to search
Line 1: Line 1:
MECHANICAL DESIGN (Paulo, Steve L.)
+
'''MECHANICAL DESIGN''' (Paulo, Steve L.)
  
 
* No significant changes in design since ERR
 
* No significant changes in design since ERR
  
* Action item: steps towards assembly and commissioning:
+
* '''Action item''': steps towards assembly and commissioning:
 
::* Check and document interference for all kinematics again including those for the DVCS experiment from Hall A
 
::* Check and document interference for all kinematics again including those for the DVCS experiment from Hall A
 
::* dDocument time estimates for configuration changes, e.g. moving the NPS from one side to the other, rotating the magnet
 
::* dDocument time estimates for configuration changes, e.g. moving the NPS from one side to the other, rotating the magnet
 
::* Identify and document items that can be done in advance of installation, e.g. welding the plates on the SHMS (requires finishing the drawings)
 
::* Identify and document items that can be done in advance of installation, e.g. welding the plates on the SHMS (requires finishing the drawings)
  
MAGNET (Charles)
+
'''MAGNET''' (Charles)
  
 
* Magnet was energized to 25% (250A) of the max current
 
* Magnet was energized to 25% (250A) of the max current
Line 16: Line 16:
 
* Running at lower current also has an impact on the HMS optics design
 
* Running at lower current also has an impact on the HMS optics design
  
* Action Items:
+
* '''Action Items:'''
 
::* Check measurements vs 3D calculations
 
::* Check measurements vs 3D calculations
 
::* Make table of fringe fields vs. current and check simulations for physics impact
 
::* Make table of fringe fields vs. current and check simulations for physics impact
 
::* Decide on what fraction of maximum current to run the magnet for first run group – will also impact HMS optics
 
::* Decide on what fraction of maximum current to run the magnet for first run group – will also impact HMS optics
  
DETECTOR FRAME OVERVIEW (Emmanuel)
+
'''DETECTOR FRAME OVERVIEW''' (Emmanuel)
  
 
* Final design
 
* Final design
Line 47: Line 47:
 
::* heat exchanger air flow - optimized, not much overall since many cables
 
::* heat exchanger air flow - optimized, not much overall since many cables
  
* Action Items
+
* '''Action Items'''
 
::* Finalize quotes, e.g. for quartz and mu metal
 
::* Finalize quotes, e.g. for quartz and mu metal
 
::* Implement the new magnetic shielding design – includes ordering all parts (honeycomb, mu metal, iron shielding, aluminum plates, supports), assembly, and testing
 
::* Implement the new magnetic shielding design – includes ordering all parts (honeycomb, mu metal, iron shielding, aluminum plates, supports), assembly, and testing
Line 58: Line 58:
 
::* Determine if there is a way to monitor thickness increase of crystals when adding tape
 
::* Determine if there is a way to monitor thickness increase of crystals when adding tape
  
DETECTOR BOX (Laurent)
+
'''DETECTOR BOX''' (Laurent)
  
 
* Built and assembled
 
* Built and assembled
Line 64: Line 64:
 
* Discussion about mounting holes to install the box on the JLab fixture (once installed, all lifting will be done from the JLab fixture)
 
* Discussion about mounting holes to install the box on the JLab fixture (once installed, all lifting will be done from the JLab fixture)
  
* Action items:
+
* '''Action items:'''
 
::* re-calculate center of gravity
 
::* re-calculate center of gravity
 
::* decide on how to attach NPS frame to JLab fixture - bolts, weld?
 
::* decide on how to attach NPS frame to JLab fixture - bolts, weld?
  
PCB, CABLES, ELECTRICAL (Thi)
+
'''PCB, CABLES, ELECTRICAL''' (Thi)
  
 
* Interface bases, HV-LED - Fischer connectors
 
* Interface bases, HV-LED - Fischer connectors
Line 82: Line 82:
 
::* developed special tool for these tests
 
::* developed special tool for these tests
  
 
+
'''CRYSTALS''' (Vladimir)
CRYSTALS (Vladimir)
 
  
 
* Have been receiving crystals from CRYTUR and characterizing - 100% acceptance
 
* Have been receiving crystals from CRYTUR and characterizing - 100% acceptance
Line 96: Line 95:
 
* 700 PMTs are on site
 
* 700 PMTs are on site
  
* Action items:
+
* '''Action items:'''
 
::* Send 10 CRYTUR crystals and full-size glass to Orsay for irradiation tests
 
::* Send 10 CRYTUR crystals and full-size glass to Orsay for irradiation tests
 
::* Decide on final stacking configuration – current nominal configuration is two outer layers SICCAS, rest CRYTUR
 
::* Decide on final stacking configuration – current nominal configuration is two outer layers SICCAS, rest CRYTUR
 
::* Check with CRYTUR if possible to expedite crystal production of outstanding 250 crystals with an early FY21 procurement
 
::* Check with CRYTUR if possible to expedite crystal production of outstanding 250 crystals with an early FY21 procurement
  
HV DIVIDERS (Fernando, Julie)
+
'''HV DIVIDERS''' (Fernando, Julie)
  
 
* All dividers are assembled at OU and awaiting decision on specifics of the modification
 
* All dividers are assembled at OU and awaiting decision on specifics of the modification
Line 110: Line 109:
 
* Reasonably good linearity at gain 3 - still analyzing anode current
 
* Reasonably good linearity at gain 3 - still analyzing anode current
  
* Action items:
+
* '''Action items:'''
 
::* Check on the method to measure anode current, e.g. in Hall C
 
::* Check on the method to measure anode current, e.g. in Hall C
 
::* Further analyze existing anode current data from Hall D
 
::* Further analyze existing anode current data from Hall D

Revision as of 15:46, 7 February 2020

MECHANICAL DESIGN (Paulo, Steve L.)

  • No significant changes in design since ERR
  • Action item: steps towards assembly and commissioning:
  • Check and document interference for all kinematics again including those for the DVCS experiment from Hall A
  • dDocument time estimates for configuration changes, e.g. moving the NPS from one side to the other, rotating the magnet
  • Identify and document items that can be done in advance of installation, e.g. welding the plates on the SHMS (requires finishing the drawings)

MAGNET (Charles)

  • Magnet was energized to 25% (250A) of the max current
  • Simulations have shown that for DVCS/pi0 it would be sufficient to energize the magnet to 2/3 of the max current - this allows to relax the requirements for a full current test. However, note that for RCS need the full field to deflect electrons
  • Running at lower current also has an impact on the HMS optics design
  • Action Items:
  • Check measurements vs 3D calculations
  • Make table of fringe fields vs. current and check simulations for physics impact
  • Decide on what fraction of maximum current to run the magnet for first run group – will also impact HMS optics

DETECTOR FRAME OVERVIEW (Emmanuel)

  • Final design
  • support structure has been built
  • new shielding design was adapted
  • no change in cooling strategy
  • PMT assembly concept ready (see a prototype here)
  • attachment PMT-crystal through optical grease - some rotation is possible, note that it is important to check alignment from the front during installation
  • HV and LEMO connectors on top of the box as before
  • Parts manufacturing
  • Large fraction has been received or is expected to arrive in mid-February; some delay in parts related to new shielding strategy, but still expect delivery of frame by August 2020
  • Optical fibers: 28mm diameter quartz fiber
  • Cut and polishing will be done in Orsay
  • Carbon holders
  • radiation hardness was tested in Hall C near the scattering chamber (see log entries 3687981 and 3669952)- the samples are radiation hard
  • can support the crystals - note that the crystals, in particular the bottom row, also support themselves
  • Infrastructure
  • Temperature sensors (63 front + 63 side), PT 100 Ohm
  • goal is to measure crystal temperature, no feedback, no interlock, but should be in alarm handler
  • radiation concerns when operating in the hall
  • Chiller - radiation concerns
  • heat exchanger air flow - optimized, not much overall since many cables
  • Action Items
  • Finalize quotes, e.g. for quartz and mu metal
  • Implement the new magnetic shielding design – includes ordering all parts (honeycomb, mu metal, iron shielding, aluminum plates, supports), assembly, and testing
  • Send temperature control information to Brad to figure out readout (include in alarm handler, but no feedback, no interlock)
  • Determine needs for operating chiller in Hall C, e.g. shielding, order spares
  • Send crystal wrapping material for pre-shaping to JLab
  • Check uniformity of fiber transmittance after cut/polish
  • Test for LED system cross talk for adjacent PMTs
  • Check if Kapton tape should be used around the PMT to insulate it from the mu metal cylinder
  • Determine if there is a way to monitor thickness increase of crystals when adding tape

DETECTOR BOX (Laurent)

  • Built and assembled
  • Discussion about mounting holes to install the box on the JLab fixture (once installed, all lifting will be done from the JLab fixture)
  • Action items:
  • re-calculate center of gravity
  • decide on how to attach NPS frame to JLab fixture - bolts, weld?

PCB, CABLES, ELECTRICAL (Thi)

  • Interface bases, HV-LED - Fischer connectors
  • HV cables (Samtec)
  • tested wires in each cable to detect short circuits, bad connections
  • tested HV on each cable
  • Anode cables - waiting for LEMO connector, SMA side done
  • Systec + LPC
  • LED cables tested in similar way as HV cables
  • developed special tool for these tests

CRYSTALS (Vladimir)

  • Have been receiving crystals from CRYTUR and characterizing - 100% acceptance
  • September 2020: expect to have ~630 crystals
  • April 2021: expect to have 900 CRYTUR crystals
  • rate of production is 30-40 crystals/month with PANDA or other production ongoing - most recently 30 pieces/month
  • fastest production rate was 250 crystals/3 months
  • slowest production rate is anticipated to be 15-20 crystals/month, e.g. with large PANDA order in parallel
  • Have 460 SICCAS crystals on site
  • 700 PMTs are on site
  • Action items:
  • Send 10 CRYTUR crystals and full-size glass to Orsay for irradiation tests
  • Decide on final stacking configuration – current nominal configuration is two outer layers SICCAS, rest CRYTUR
  • Check with CRYTUR if possible to expedite crystal production of outstanding 250 crystals with an early FY21 procurement

HV DIVIDERS (Fernando, Julie)

  • All dividers are assembled at OU and awaiting decision on specifics of the modification
  • Nonlinearity of bypassed amplifier is 1-2% depending on pre-amp gain (0.5, 1, 2 V to match fADC)
  • gain 3: nonlinearity increases to ~4% (2 V) and ~11% (0.5V)
  • Reasonably good linearity at gain 3 - still analyzing anode current
  • Action items:
  • Check on the method to measure anode current, e.g. in Hall C
  • Further analyze existing anode current data from Hall D
  • Decide on final HV divider gain
  • Determine need for additional resources and/or funding beyond what was planned

DAQ, ELECTRONICS, HV (Brad)


Additional Notes by Charles Hyde

•Summarize full to-do list in hall, and estimated time to completion
•Estimate time for configuration changes during beam running
•Document interferences between NPS, BeamLine, HMS
•Kinematic configurations are dynamic (addition of beam time from E12-06-114, uncertain beam energy in 2022)
• How is the Calorimeter, Cabling, etc assembled
•Do we run Sweep Magnet at full power or ~30%?
•DVCS, pi0 maybe OK at 30% power
•Future RCS will require full power (with NPS on outer side of SHMS)
• Do we mix-and-match Crytur and SICCAS crystals?
•Order ~200 more crystals from Crytur and wait ~1year for full delivery?