Difference between revisions of "General EEEMCal Meeting Summary 11/19/21"
Jump to navigation
Jump to search
Line 79: | Line 79: | ||
::* procurement would then start in ~Sept 2023 and all blocks must be delivered within at most 4 years | ::* procurement would then start in ~Sept 2023 and all blocks must be delivered within at most 4 years | ||
− | * Actions for start of long-lead procurement | + | * '''Actions for start of long-lead procurement''' |
::* Crystal: need module design 90% complete by Spring 2023 | ::* Crystal: need module design 90% complete by Spring 2023 | ||
:::* Need specifications: dimensions, optical characteristics (light yield, transmission, ...), radiation hardness | :::* Need specifications: dimensions, optical characteristics (light yield, transmission, ...), radiation hardness |
Latest revision as of 10:30, 19 November 2021
PARTICIPANTS: A. Bazilevsky, C. Munoz-Camacho, Crytur-USA, D. Hasell, H. Mkrtchyan, H. Marukyan, M. Finger, R. Reed, V. Berdnikov, T. Horn, R. Fatemi
EEEMCAL IN DETECTOR PROPOSALS
- Draft text from ATHENA and ECCE proposals posted - CORE expected to come soon
- Comment on Fig. pion rejection in ECCE proposal - expect PWO and SciGlass performance to be similar, at first glance this fact not clear since there is a lot of information presented in the figure, is there a way to simplify?
- Authorship:
- done by institution
- many EEEMCAL institutions will be listed on all proposals - IB representative from each institution has to communicate the desired authors to the proto-collaborations (ATHENA: email to Ernst, ECCE: update GoogleSheet, CORE: email Charles/Pawel)
SIMULATIONS
- ECCE: Orsay team produced performance plots
- ATHENA: AANL team working on performance plots
- Note that for the performance plots for the YR an ideal case was assumed
- no materials
- no gaps
- Gaussian distributions
DESIGN
- Design technical note posted and circulated to all proto-collaborations
- Reference for the EEEMCAL design note: EEEMCAL Mechanical Design and Integration, J. Bettane, C. Munoz-Camacho, V1.2 (Nov 2021)
PROTOTYPE BEAM TESTS
JLAB
- Completed beam tests with PWO and SciGlass (2cm x 2cm x 20cm) and different readout schemes (PMT, SiPM)
- Array: 3x3
- SiPM configurations: 4 SiPM/crystal and 16 SiPM/crystal (Crytur-USA prototype)
- Initial results shown for PWO and SciGlass
- Note: the 3x3 calorimeter was not calibrated due to time constraints - would really need to calibrate channel-by-channel
- Action: visualization of the tails - note that the current fit is central core - will be improved in more detailed analysis using crystal ball function (Link); note: in general as long as fits to data and simulation are performed in the same way should be ok to compare the results
- Crytur-USA prototype
- 3x3 array featuring 16SiPMs per crystal - combined readout, no noise observed in the lab
- issues with temperature rising in the detector box
- initially observed during cosmic tests via missing signals - but at that time unclear if missing signals were due to trigger, temperature, etc.
- after beam tests temperature was measured with an external probe to be 100F near the sensors (and probably even higher inside the box); no signals were observed from beam test
- possible reason for increased temperature: box was made light tight by closing it with a cover that may have restricted air flow
- some data are available for analysis from cosmics test
- additional optimizations planned: adjustable gain
DESY
- Successfully set up 5x5 PWO+PMT and began debugging/gain matching etc.
- Planning 3 different readout configurations (QCD, CAEN digitizer, JLab fADC250, SRO)
- Plan to start taking data this weekend
- Another period of data taking is planned for spring 2022
- opportunity to test SciGlass in 5x5 setup then
- Note: currently use 21mm wrapping in x and y
EEEMCAL IN EIC PROJECT - DISCUSSION OF LONG-LEAD PROCUREMENTS (Sasha)
- Currently have PWO crystal configurations:
- ATHENA: ~2000 blocks
- ECCE: ~3000 blocks
- Production capacity CRYTUR:
- ~500 blocks/year assuming concurrent projects other than EIC
- Maximum capacity is 720 blocks/year (60 crystals/month)
- Normal procurement starts after CD3 approval and must be at most 3 years from contract award to when blocks are delivered. At 500/year it would require more than 3 year --> long-lead procurement
- Long-lead procurement starts when CD2/CD3A is approved - planned for Spring 2023
- procurement would then start in ~Sept 2023 and all blocks must be delivered within at most 4 years
- Actions for start of long-lead procurement
- Crystal: need module design 90% complete by Spring 2023
- Need specifications: dimensions, optical characteristics (light yield, transmission, ...), radiation hardness
- SiPMs: need configuration and specs design complete by Spring 2023 - note: SiPMs included in Long-Lead Procurement since whole detector needs on order 1 million and vendor would need more than 4 years to produce them
- Need specifications: pixel size, how many per crystal, etc.
- Note on Lead Glass
- About 9000 blocks available from Phenix - would need readout, some refurbishment etc.
- Note on SciGlass
- for readout of large cross section 4x4 need some more detail on how it is envisioned, e.g., using light guides or more SiPMs per block
BRIEF REMINDER ABOUT FUNDING PATH
- Have an R&D plan posted on the Wiki (Link) with distribution of tasks globally
- Expect NSF MSRI funding proposal submissions in January 2023 - by that time refine the tasks and which group(s) take on which components for asking for funding, also including international agencies (Armenia, Czech Republic, France)
NEXT MEETING: 10 DECEMBER AT 8:30AM ET