Difference between revisions of "Detailed List of Activities"

From Cuawiki
Jump to navigation Jump to search
Line 22: Line 22:
  
 
3x3 prototype re-re-alignment (5+3mm), ''October 19 (Vlad, Arshak)''
 
3x3 prototype re-re-alignment (5+3mm), ''October 19 (Vlad, Arshak)''
 +
 +
3x3 prototype HV base replacement (October 27, Yeran, Arthur, Arshak)
 +
https://userweb.jlab.org/~yeran/SciGlass/3x3-HV.pdf
 +
 +
3x3 prototype central channel(#5) HV divider/base replacement (Yeran, Arshak)
 +
https://userweb.jlab.org/~yeran/SciGlass/3x3-HV-updated.pdf

Revision as of 13:07, 28 October 2022

<-- Back to Beam Tests Page

Visual inspection of the SciGlass date?? Josh??

Transmittance measurement September 16 (Josh, Yeran)

Dimensions measurement September 29 (Josh, Yeran)

Module assembly October 13 (Josh, Yeran)

Beam test with 12x1 array in the Hall, September 29 (Vlad, Arshak)

12x1 array removing from the hall October 6 (Yeran, Arshak)

3x3 prototype cosmic test in clean room, October 11 (Yeran, Arshak)

3x3 prototype box assembling October 13 (Josh, Yeran)

3x3 prototype installation in the hall and alignment October 14 (Yeran, Vlad, Arshak, Sasha)

3x3 prototype re-alignment (5mm), October 18 (Yeran, Arshak, Sasha)

3x3 prototype re-re-alignment (5+3mm), October 19 (Vlad, Arshak)

3x3 prototype HV base replacement (October 27, Yeran, Arthur, Arshak) https://userweb.jlab.org/~yeran/SciGlass/3x3-HV.pdf

3x3 prototype central channel(#5) HV divider/base replacement (Yeran, Arshak) https://userweb.jlab.org/~yeran/SciGlass/3x3-HV-updated.pdf