* '''May 3rd''': NPS detector moves to Hall C
 
* '''May 3rd''': NPS detector moves to Hall C
  
* '''May 15 - May 30''': connect cables to the NPS detector
+
* '''May 15 - May 30''': connect cables to the NPS detector ([https://docs.google.com/spreadsheets/d/1zvJLaskBxPr61IM0zkmumfyurz3CvkXzL0oiQSEl2Ss/edit#gid=0 installation tasks])
  
 
* '''June 1 - July 14''': NPS detector checkout in Hall C
 
* '''June 1 - July 14''': NPS detector checkout in Hall C
  
 
* '''July 17''': NPS Experiments Phase 1 start
 
* '''July 17''': NPS Experiments Phase 1 start

Latest revision as of 14:53, 7 February 2023

Timeline

  • February - pre-installation tasks (see: link)
  • complete calorimeter trigger
  • upgrade HMS DAQ
  • calorimeter tests
  • March - pre-installation tasks (see: link)
  • complete calorimeter trigger
  • upgrade HMS DAQ
  • calorimeter tests
  • April 15 - April 30: start disconnecting cables from NPS in EEL108
  • disconnect cables
  • bundle cables and prepare for transport
  • May 3rd: NPS detector moves to Hall C
  • June 1 - July 14: NPS detector checkout in Hall C
  • July 17: NPS Experiments Phase 1 start