(Created page with "PARTICIPANTS: Afnan Shatat, Holly, Carlos, Douglas, Tanja, Ethan, Matthew Nguyen, Renee, Rosi, Larry, Justin, Sasha, Vardan, Joerg, Hrachya, Julie, Hamlet, DESY BEAM TEST P...")
 
Line 44: Line 44:
  
 
* Discussion about documentation and upcoming final design review
 
* Discussion about documentation and upcoming final design review
::* Action: need to identify a good way to generate the needed documentation
+
::* '''Action''': need to identify a good way to generate the needed documentation
 
:::* how are previous documentations folded in?
 
:::* how are previous documentations folded in?
 
:::* how are recent/ongoing beam tests folded in?
 
:::* how are recent/ongoing beam tests folded in?

Revision as of 10:52, 7 February 2025

PARTICIPANTS: Afnan Shatat, Holly, Carlos, Douglas, Tanja, Ethan, Matthew Nguyen, Renee, Rosi, Larry, Justin, Sasha, Vardan, Joerg, Hrachya, Julie, Hamlet,


DESY BEAM TEST PREPARATION

  • Overall Goal of the February test: test different readout chains (e.g., discrete vs. ASIC) with Orsay prototype
  • Orsay prototype is ready. Will be shipped to DESY with expected arrival on 12 Feb
  • some personnel will arrive on Friday 2/14 to start setting up DAQ; assembly of the prototype will follow on Monday after the safety lecture as some personnel need to pass that training
  • Discrete readout chain preparation are on track
  • PCBs arrived at JLab and were sent on to Gerard after minor modifications
  • Larry has been working on the power cables/distribution box and has sent them on to Gerard
  • Gerard is planning to do some tests of both
  • Justin will pick up all components from Gerard including a LV power supply and bring everything to DESY
  • An overall run plan for the February beam test has been discussed - details are still being sorted
  • Next beam test preparation meeting is on 11 February at 10:30AM ET
  • Looking ahead there are 2-3 additional beam tests planned:
  • 24 March++ at DESY: direct comparison of PMT/SiPM, Crytur prototype with different readout and chain, and any additional readout chain tests based on February investigation
  • is any pulse shaping needed for the PMTS? Note that the same digitizer (V1725) has been used in previous beam tests with PMT. May need to review the details
  • June at DESY: contingency. Need to start coordinating this beam slot as Douglas and Ethan will likely not be available or not available for the entire time
  • June/July at JLAB: initial discussions have started on how to integrate the ASIC based readout with the HD infrastructure, but need to follow up on the details


NSF PROPOSAL

  • Discussion about possible proposal planning
  • Given that the proposal submission deadline is still posted as 19 March 2025 and the review uncertainty it may be wise to give SPOs a heads up


OTHER

  • Discussion with ePIC-DSC on 7 Feb
  • discussion in EEEMCAL context about the points circulated by ePIC TC
  • Carlos/Tanja will report from the meeting
  • Discussion about ongoing reports
  • European strategy plan is out for review
  • pre TDR time line more relaxed - summer to end of year
  • Discussion about documentation and upcoming final design review
  • Action: need to identify a good way to generate the needed documentation
  • how are previous documentations folded in?
  • how are recent/ongoing beam tests folded in?


NEXT MEETING: FRIDAY 21 FEBRUARY AT 8:00 AM ET