Line 50: Line 50:
  
 
NEXT MEETING: FRIDAY 21 FEBRUARY AT 8:00 AM ET
 
NEXT MEETING: FRIDAY 21 FEBRUARY AT 8:00 AM ET
 +
 +
 +
TC-DSC MEETING 7 Feb 2025 - Notes
 +
 +
* Overall EEEMCAL in good shape and moving along at a reasonable pace
 +
 +
* Workforce
 +
::* simulation has been weak. Have expert from UKY and personnel from AANL. Unclear how one would fill in more personnel
 +
 +
* Final design review planning
 +
::* mechanical design at the required level
 +
::* remaining item is the readout chain details - have beam test planned at DESY and at JLAB and hope to have the information very soon
 +
 +
* Long lead procurement crystals - any specifications still needed?
 +
::* No. Had final design review and specifications have been set.
 +
 +
* NSF proposal status
 +
::* deadline for full proposal submission (by invitation based on pre-proposal) is on 19 March 2025. Pre-proposal was submitted and awaiting feedback.
 +
 +
* Documentation
 +
::* Discussing preparation of a tech note independent of pre-TDR. This written documentation could be used as pre-brief for a final design review and as reference material for pre-TDR or a future EEEMCAL publication
 +
 +
* Cooling
 +
::* idea is to have a standalone design to cool the EEEMCAL and some safety margin for external sources
 +
::* planned are simulations and prototype tests for the cooling
 +
 +
* Light monitoring/calibration system status
 +
::* EEEMCAL will use LEDs for light monitoring, but not calibration
 +
::* A concept exists from NPS
 +
 +
* ASIC - any dependence on the ePIC chip development
 +
::* No. EEEMCAL uses HCGROC - have all information available for making decisions for EEEMCAL

Revision as of 11:39, 7 February 2025

PARTICIPANTS: Afnan Shatat, Holly, Carlos, Douglas, Tanja, Ethan, Matthew Nguyen, Renee, Rosi, Larry, Justin, Sasha, Vardan, Joerg, Hrachya, Julie, Hamlet,


DESY BEAM TEST PREPARATION

  • Overall Goal of the February test: test different readout chains (e.g., discrete vs. ASIC) with Orsay prototype
  • Orsay prototype is ready. Will be shipped to DESY with expected arrival on 12 Feb
  • some personnel will arrive on Friday 2/14 to start setting up DAQ; assembly of the prototype will follow on Monday after the safety lecture as some personnel need to pass that training
  • Discrete readout chain preparation are on track
  • PCBs arrived at JLab and were sent on to Gerard after minor modifications
  • Larry has been working on the power cables/distribution box and has sent them on to Gerard
  • Gerard is planning to do some tests of both
  • Justin will pick up all components from Gerard including a LV power supply and bring everything to DESY
  • An overall run plan for the February beam test has been discussed - details are still being sorted
  • Next beam test preparation meeting is on 11 February at 10:30AM ET
  • Looking ahead there are 2-3 additional beam tests planned:
  • 24 March++ at DESY: direct comparison of PMT/SiPM, Crytur prototype with different readout and chain, and any additional readout chain tests based on February investigation
  • is any pulse shaping needed for the PMTS? Note that the same digitizer (V1725) has been used in previous beam tests with PMT. May need to review the details
  • June at DESY: contingency. Need to start coordinating this beam slot as Douglas and Ethan will likely not be available or not available for the entire time
  • June/July at JLAB: initial discussions have started on how to integrate the ASIC based readout with the HD infrastructure, but need to follow up on the details


NSF PROPOSAL

  • Discussion about possible proposal planning
  • Given that the proposal submission deadline is still posted as 19 March 2025 and the review uncertainty it may be wise to give SPOs a heads up


OTHER

  • Discussion with ePIC-DSC on 7 Feb
  • discussion in EEEMCAL context about the points circulated by ePIC TC
  • Carlos/Tanja will report from the meeting
  • Discussion about ongoing reports
  • European strategy plan is out for review
  • pre TDR time line more relaxed - summer to end of year
  • Discussion about documentation and upcoming final design review
  • Action: need to identify a good way to generate the needed documentation
  • how are previous documentations folded in?
  • how are recent/ongoing beam tests folded in?


NEXT MEETING: FRIDAY 21 FEBRUARY AT 8:00 AM ET


TC-DSC MEETING 7 Feb 2025 - Notes

  • Overall EEEMCAL in good shape and moving along at a reasonable pace
  • Workforce
  • simulation has been weak. Have expert from UKY and personnel from AANL. Unclear how one would fill in more personnel
  • Final design review planning
  • mechanical design at the required level
  • remaining item is the readout chain details - have beam test planned at DESY and at JLAB and hope to have the information very soon
  • Long lead procurement crystals - any specifications still needed?
  • No. Had final design review and specifications have been set.
  • NSF proposal status
  • deadline for full proposal submission (by invitation based on pre-proposal) is on 19 March 2025. Pre-proposal was submitted and awaiting feedback.
  • Documentation
  • Discussing preparation of a tech note independent of pre-TDR. This written documentation could be used as pre-brief for a final design review and as reference material for pre-TDR or a future EEEMCAL publication
  • Cooling
  • idea is to have a standalone design to cool the EEEMCAL and some safety margin for external sources
  • planned are simulations and prototype tests for the cooling
  • Light monitoring/calibration system status
  • EEEMCAL will use LEDs for light monitoring, but not calibration
  • A concept exists from NPS
  • ASIC - any dependence on the ePIC chip development
  • No. EEEMCAL uses HCGROC - have all information available for making decisions for EEEMCAL