Meeting 30 July 2021
Jump to navigation
Jump to search
DISCUSSION ITEMS
- Rotating target updates
- Design models, stress/thermal calculations
- Engineering analysis and planning
- TCS updates
- Transverse polarized TCS Brannon Semp (VT) single & double spin asymmetries for TCS
- Other
PARTICIPANTS: Amy Comer, Bert Metzger, Bogdan Wojtsekhowski, Brannon Semp, Dustin Keller, Rolf Ent, Hamlet Mkrtchyan, Josh Crafts, Kevin, Marie Boer, Vardan Tadevosyan, Tanja Horn
DESIGN/ENGINEERING (Amy, Bert, Bogdan, Gabriel, Josh)
- Cooling system work ongoing
- Power deposition along z has been updated
- Testing part of absorber
- Materials
- First tungsten powder blocks for inner part of magnet arrived
- Checking on sintered (still have to shim) tungsten blocks - cost increased over years - need to look into optimization of shielding (main focus on front since most radiation there), dimensions roughly ~3"x(4-5)"x6"
- Change of procurement plan
- initially hoped that get magnet out for procurement, but will still take
- move towards tungsten and start procurement of high density tungsten blocks (16 g/cm3) for center region ~20% of blocks needed
- Action items:
- Check on number of tungsten blocks needed - with 16 g/cm3 and for earlier block size (2 x 4 x 4) assumption ~19.4 (metric) tons
- Start the procurement for the inner part of the shielding
- From later discussion on Tungsten bricks:
- 19.43 metric tons or ~2109 bricks of 2 x 4 x 4
- For the larger bricks of Elmet of 3" x 4.125" x 6.2" that would be ~880.
ROTATING TARGET UPDATE (Dustin)
- Two design options
- standard - limited to one cup, likely will require frequent changes of bellows (quantify)
- new - can take more than one cup, design to optimize bellow wear
- Standard prototype has been built - still needs to be tested (cool down and in beam at NIST)
- New design does not yet have a prototype
- Action item: further develop a plan toward realizing a rotating target for the experiments
TCS TRANSVERSE POLARIZED (Brannon)
- Additional science that could be done within the time of the current C2 approved TCS proposal
- Need to check rates and backgrounds etc.
- Action items:
- focus on removing C2 conditional on TCS proposal first - aim for completing in next four months
- evaluate experimental details of new science in 2022
NEXT MEETING: FRIDAY 27 AUGUST AT 8AM ET