MAGNET (Charles, Bogdan, Paulo, Rolf)
- Mapper was delivered to JLab - some alignment modifications are being made
- OSP for magnet mapping in test lab almost ready
- Another OSP is needed for the magnet operation in Hall C
- Fringe field considerations on HMS axis - affects optics
- <200G, calculation good enough
- for close approach NPS and HMS configuration without shelf may be better
HV Divider (Fernando, Vladimir, Alex S.)
- Actual amplifier gain may be ~28 (instead of ~10 as thought based on description)
- Modified amplifiers being prepared
- 3x3 prototype for beam tests in Hall D with HV divider with modified amplifier ready
- allows for energy comparison
- goal is to compare different amplifier gains, but also different crystals - start with Crytur
FRAME (Carlos)
- Frame mock-up constructed and being used to determine optimal cable lengths
- PCB assembly ongoing
- Discussion about cable assembly - France or JLab
SIMULATION (Ho San)
- Simulation in good shape - energy resolution, longitudinal and lateral energy deposition
CRYSTALS (Vladimir, Tanja)
- Discussion about inspection of 160 SICCAS replacement crystals
- ~54% pass
- Significant fraction of crystals have nonuniform sizes along crystal and smaller than specs
- Crytur update
- next part of CUA order is on the way (currently have 18/55)
- additional orders placed for 45 by OU and 100(+50) by JLab
- expected capacity for future orders: 120 in calendar year 2019, 180-240/year for the next two years
NEXT MEETING: THURSDAY 4 APRIL AT 9AM (ET)