Summary 2/3/20
Jump to navigation
Jump to search
MECHANICAL DESIGN
- No significant changes in design since ERR
- Action item: steps towards assembly and commissioning:
- Check and document interference for all kinematics again including those for the DVCS experiment from Hall A
- dDocument time estimates for configuration changes, e.g. moving the NPS from one side to the other, rotating the magnet
- Identify and document items that can be done in advance of installation, e.g. welding the plates on the SHMS (requires finishing the drawings)
MAGNET
- Magnet was energized to 25% (250A) of the max current
- Simulations have shown that for DVCS/pi0 it would be sufficient to energize the magnet to 2/3 of the max current - this allows to relax the requirements for a full current test. However, note that for RCS need the full field to deflect electrons
- Running at lower current also has an impact on the HMS optics design
- Action Items:
- Check measurements vs 3D calculations
- Make table of fringe fields vs. current and check simulations for physics impact
- Decide on what fraction of maximum current to run the magnet for first run group – will also impact HMS optics
DETECTOR FRAME
- Final design
- support structure has been built
- new shielding design was adapted
- no change in cooling strategy
- PMT assembly concept ready (see a prototype here)
- attachment PMT-crystal through optical grease - some rotation is possible, note that it is important to check alignment from the front during installation
- Parts manufacturing
- Large fraction has been received or is expected to arrive in mid-February; some delay in parts related to new shielding strategy, but still expect delivery of frame by August 2020
- Optical fibers: 28mm diameter quartz fiber
- Cut and polishing will be done in Orsay
- Check uniformity of transmittance
- Carbon holders
- radiation hardness was tested in Hall C
Additional Notes by Charles Hyde
- •Summarize full to-do list in hall, and estimated time to completion
- •Estimate time for configuration changes during beam running
- •Document interferences between NPS, BeamLine, HMS
- •Kinematic configurations are dynamic (addition of beam time from E12-06-114, uncertain beam energy in 2022)
- • How is the Calorimeter, Cabling, etc assembled
- •Do we run Sweep Magnet at full power or ~30%?
- •DVCS, pi0 maybe OK at 30% power
- •Future RCS will require full power (with NPS on outer side of SHMS)
- • Do we mix-and-match Crytur and SICCAS crystals?
- •Order ~200 more crystals from Crytur and wait ~1year for full delivery?