Participants:
- University Roma Tor Vergata and INFN Roma Tor Vergata: R. Ammendola, B. Benkel, A. D'Angelo, R. Di Salvo, A. Fantini, L. Lanza, G. Nobili, E. Sidoretti, E. Tusi
- INFN Catania: M. Bondì
- Temple University: Matt Posik, Bernd Surrow, Jae Nam
- Thomas Jefferson National Accelerator Facility: Kondo Gnanvo, Seungjoon Lee
General Information
Wednesday Zoom meetings:
https://jlab-org.zoomgov.com/j/16161557979?pwd=SUxJUjF3cmF1S0swV3ZtMForTWRKUT09
Friday Zoom meetings:
https://jlab-org.zoomgov.com/j/1601293500?pwd=d0VseUh0NGwwNExjQ0NON3NLSW9JUT09
ePIC - EIC Roma2 MPGd endcaps - To Do list
Detector Geometry Studies
Activity | Persons in charge |
Understand the Mechanical envelope available for uRwell endcaps | Seung Joon (JLab) |
Define the detector active area | ... |
Final segmentation – 4 quadrants vs 2 semi-circles | ... |
Servings & Cooling | Seung Joon (JLab) |
Electronic cables | Irakli Damien (Saclay) |
Geometrical Constraints for/of SALSA FEB | Saclay group - Roberto Ammendola |
Read-out system definition (X,Y) vs (R,phi) , pitch | ... |
Material budget assessment ( with/without GEM preamplifier) | ... |
Gap-size definition (with or without GEM foil) | ... |
Mounting procedure and related constraints | ... |
Simulations and software
Activity | Persons in charge |
Detector geometry simulation | Mariangela, Matt, Lucilla |
Detector response simulation | Mariangela, Matt, Lucilla |
Data analysis algorithm: standard cluster reconstruction and uTPC version | Bruno, Rachele |
Inclusion of endcap response in the ePIC tracking | Bruno, Rachele |
Final performances assessment | ... |
Integration and Hardware
Activity | Persons in charge |
On-Line Calibration -> Alignment -> SVT/Tracking->TIC: survey/photogrammetry plans – targets to be installed | ... |
Study of stability against magnetic field forces (2 Tesla) (carbon fiber support) | ... |
Detector Support and mounting scheme | ... |
R&D prototype tests
Activity | Persons in charge |
SRS DAQ set-up | Elena |
SRS data analysis framework (corrywreckan..) | Elena |
Gas handling system | ... |
Humidity probes | Elena+ Giulietto |
HV supply | ...
|
Plastic scintillators and DAQ trigger | ... |
Trigger NIM daisy chain (low thr discr, coincidence unit, dual timer, logic fan in fan out) | ... |
Reference trackers set-up (CS 2D detectors?) | Elena |
On-line monitoring - Labview | ... |
Mechanical structure | ... |
General Information
See the following document for information:
https://docs.google.com/spreadsheets/d/1dY-NObNM8xuIHnAaDR1pqd_40PR8eiPVgmk5vhvuKys/edit?gid=0#gid=0
Wednesday group meetings in 2024
Friday group meetings in 2024
May 10, 2024 | May 24, 2024 |
Useful Links
Documentation
Presentation to ePIC Referees - 2025 slides