Summary 2/3/20
Jump to navigation
Jump to search
MECHANICAL DESIGN (Paulo, Steve L.)
- No significant changes in design since ERR
- Action item: steps towards assembly and commissioning:
- Check and document interference for all kinematics again including those for the DVCS experiment from Hall A
- dDocument time estimates for configuration changes, e.g. moving the NPS from one side to the other, rotating the magnet
- Identify and document items that can be done in advance of installation, e.g. welding the plates on the SHMS (requires finishing the drawings)
MAGNET (Charles)
- Magnet was energized to 25% (250A) of the max current
- Simulations have shown that for DVCS/pi0 it would be sufficient to energize the magnet to 2/3 of the max current - this allows to relax the requirements for a full current test. However, note that for RCS need the full field to deflect electrons
- Running at lower current also has an impact on the HMS optics design
- Action Items:
- Check measurements vs 3D calculations
- Make table of fringe fields vs. current and check simulations for physics impact
- Decide on what fraction of maximum current to run the magnet for first run group – will also impact HMS optics
DETECTOR FRAME OVERVIEW (Emmanuel)
- Final design
- support structure has been built
- new shielding design was adapted
- no change in cooling strategy
- PMT assembly concept ready (see a prototype here)
- attachment PMT-crystal through optical grease - some rotation is possible, note that it is important to check alignment from the front during installation
- HV and LEMO connectors on top of the box as before
- Parts manufacturing
- Large fraction has been received or is expected to arrive in mid-February; some delay in parts related to new shielding strategy, but still expect delivery of frame by August 2020
- Optical fibers: 28mm diameter quartz fiber
- Cut and polishing will be done in Orsay
- Carbon holders
- Infrastructure
- Temperature sensors (63 front + 63 side), PT 100 Ohm
- goal is to measure crystal temperature, no feedback, no interlock, but should be in alarm handler
- radiation concerns when operating in the hall
- Chiller - radiation concerns
- heat exchanger air flow - optimized, not much overall since many cables
- Action Items
- Finalize quotes, e.g. for quartz and mu metal
- Implement the new magnetic shielding design – includes ordering all parts (honeycomb, mu metal, iron shielding, aluminum plates, supports), assembly, and testing
- Send temperature control information to Brad to figure out readout (include in alarm handler, but no feedback, no interlock)
- Determine needs for operating chiller in Hall C, e.g. shielding, order spares
- Send crystal wrapping material for pre-shaping to JLab
- Check uniformity of fiber transmittance after cut/polish
- Test for LED system cross talk for adjacent PMTs
- Check if Kapton tape should be used around the PMT to insulate it from the mu metal cylinder
- Determine if there is a way to monitor thickness increase of crystals when adding tape
DETECTOR BOX (Laurent)
- Built and assembled
- Discussion about mounting holes to install the box on the JLab fixture (once installed, all lifting will be done from the JLab fixture)
- Action items:
- re-calculate center of gravity
- decide on how to attach NPS frame to JLab fixture - bolts, weld?
PCB, CABLES, ELECTRICAL (Thi)
- Interface bases, HV-LED - Fischer connectors
- HV cables (Samtec)
- tested wires in each cable to detect short circuits, bad connections
- tested HV on each cable
- Anode cables - waiting for LEMO connector, SMA side done
- Systec + LPC
- LED cables tested in similar way as HV cables
- developed special tool for these tests
CRYSTALS (Vladimir)
- Have been receiving crystals from CRYTUR and characterizing - 100% acceptance
- September 2020: expect to have ~630 crystals
- April 2021: expect to have 900 CRYTUR crystals
- rate of production is 30-40 crystals/month with PANDA or other production ongoing - most recently 30 pieces/month
- fastest production rate was 250 crystals/3 months
- slowest production rate is anticipated to be 15-20 crystals/month, e.g. with large PANDA order in parallel
- Have 460 SICCAS crystals on site
- 700 PMTs are on site
- Action items:
- Send 10 CRYTUR crystals and full-size glass to Orsay for irradiation tests
- Decide on final stacking configuration – current nominal configuration is two outer layers SICCAS, rest CRYTUR
- Check with CRYTUR if possible to expedite crystal production of outstanding 250 crystals with an early FY21 procurement
HV DIVIDERS (Fernando, Julie)
- All dividers are assembled at OU and awaiting decision on specifics of the modification
- Nonlinearity of bypassed amplifier is 1-2% depending on pre-amp gain (0.5, 1, 2 V to match fADC)
- gain 3: nonlinearity increases to ~4% (2 V) and ~11% (0.5V)
- Reasonably good linearity at gain 3 - still analyzing anode current
- Action items:
- Check on the method to measure anode current, e.g. in Hall C
- Further analyze existing anode current data from Hall D
- Decide on final HV divider gain
- Determine need for additional resources and/or funding beyond what was planned
DAQ, ELECTRONICS, HV (Brad)
Additional Notes by Charles Hyde
- •Summarize full to-do list in hall, and estimated time to completion
- •Estimate time for configuration changes during beam running
- •Document interferences between NPS, BeamLine, HMS
- •Kinematic configurations are dynamic (addition of beam time from E12-06-114, uncertain beam energy in 2022)
- • How is the Calorimeter, Cabling, etc assembled
- •Do we run Sweep Magnet at full power or ~30%?
- •DVCS, pi0 maybe OK at 30% power
- •Future RCS will require full power (with NPS on outer side of SHMS)
- • Do we mix-and-match Crytur and SICCAS crystals?
- •Order ~200 more crystals from Crytur and wait ~1year for full delivery?