General Meeting Summary 3/4/21
Jump to navigation
Jump to search
PARTICIPANTS: C. Hyde, M. Boer, H. Mkrtchyan, C. Munoz-Camacho, A. Brown, P. Medeiros, R. Ent, V. Berdnikov, T. Horn, A. Asaturyan, B. Sawatzky, C. Cuevas, J. Roche, V. Tadevosyan, C. Yero, B. Wojtsekhowski,
NPS TASK LIST DISCUSSION
- Format
- Suggestion to use Gantt software to connect dependencies and resources
- Alternatively insert column "duration" and "resources" for estimates
- PMT testing
- Hamamatsu tests PMTs before shipping - documentation is included in each shipment. Try to obtain the electronic documents.
- 200 PMTs were tested in summer 2019 - no issues were found
- Time to test: 200 PMTs took 2 months
- No additional PMT testing for NPS, but may need time to select
- PMT availability: need to get replacement for ~145 PMTs that were given to Hall D for CCAL
- HV dividers
- tested 850 dividers - test on hold now until have information on if/what modifications will be made to dividers to address anode current issue
- dividers are still at OU
- Crystal wrapping
- in general takes 15-20 minutes/person
- Timeframe for organizing test lab, e.g., unpack, set up things, etc.: September - December, 2021 (estimate)
- Samtec connector
- rating is 20A
- need to check with planned HV operation conditions and document - plan to finalize these tests by 18 March 2021
- Action items:
- Circulate NPS Tasklist
- Everyone: add/edit tasks and duration and resources estimates
- Contact Hamamatsu for electronic version of PMT data sheets
NEXT MEETING: THURSDAY 1 APRIL AT 9:00 AM ET