General Meeting Summary 6/17/21
Jump to navigation
Jump to search
PARTICIPANTS: Aaron Brown, Fernando Barbosa, Bogdan Wojtsekhowski, Brannon Semp, Camille Z., Carlos Munoz-Camacho, Charles Hyde, Rolf Ent, Hamlet Mkrtchyan, Marie Boer, Paulo Medeiros, Stephen Wood, Stephen Lassiter, Vardan Tadevosyan, Tanja Horn, Alexandre Camsonne, Vladimir Berdnikov
ACTIVE HV DIVIDER (Fernando)
- Tests show signal 1 GeV equivalent
- Copper tape and ground significantly improves noise
- Need likely PMT shielding and ground
- shielding by itself will not be sufficient
- in detector would need to ground mu metal shielding (tabs with wires) - need to decide if temporary or permanent design
- Low voltage distribution
- new prototype with x10 preamp being prepared
- Overall a complex modification as detector box space very limited
- A possible alternative: use existing pin from Samtec connection - requires new cables though
- Actions:
- Scheme for PMT shield+ground and LV cable layout model
- figure out best way for low voltage distribution (e.g., quadrants)
- address question: Use 2 or 4 D-sub 37 connectors/PCB?
- Design LV distribution PCB
- Full test of new prototypes and assembly of sockets
- Scheme for PMT shield+ground and LV cable layout model
- Design currently AC coupled - could be DC coupled too
- Note that fADC is DC coupled
- In past have observed baseline drifts for DC, e.g., due to temperature - for fADC doesn't matter much since taken into account in algorithms
- DC coupled may be preferrable
- Timeline estimate
- by end of July should have good understanding of new design
- production: ~2 month from start to finish
- early October have all units and then need to assemble all sockets
- estimate: done in December
- NPS could be installed late 2022 - could run in 2023
- all assembled in place, then moved to Hall C as one unit (like ComCal)
DSG UPDATES (Aaron)
- Much progress!
- HV supply cable fabrication done
- HV supply cable testing is ongoing
- Labview Keysight Scanning program development - code development and testing
- crystal zone sensors
- hardware protection - interlock system
- temperature map
MECHANICAL UPDATE (Stephen L., Paulo)
- Detector carriage - two components: detector + cable cart
- Detector carriage in procurement
- Cable cart design - certifications pending
- Work with welding support brackets ongoing
- Support structure that attaches to SHMS, e.g., staircase, platform
- certifications ongoing
- Action: post images of detector carriage, etc.
QUESTIONS ON POWER SUPPLY FOR NPS MAGNET
- How high need to go? reversal switch needed?
- PSU with current greater than 1,100A for some overhead
- No need for polarity reversal switch
- See magnet parameter documentation here: Link
NEXT MEETING: THURSDAY 15 JULY AT 9AM ET