General Meeting Summary 9/9/21
Jump to navigation
Jump to search
PARTICIPANTS: Aaron Arshak, Bogdan, Carlos, Hamlet, Paulo, Tanja, Peter, Emmanuel, Steven, Vardan, Vladimir, Julie, Marie, Rolf, Alex
HV DIVIDERS
- All dividers and PMTs have shipped from Ohio U. and have been received at JLab
- All tests have been completed from NPS collaboration
- Action item:
- define next steps, Fernando test etc.
LV CABLING STRATEGY
- Need to take a decision now to make progress
- Action item: schedule dedicated meeting with Fernando in the week of September 13th (before 11am ET) to decide on the path forward
- Participants: Bogdan, IJCLab-Orsay, Vladimir, ....
DSG UPDATES
- Graphical interface development EPICS temperature screens
- sensors are included at front and back
- Thermal analysis: 3x3 unit with with copper shell at constant temperature 10degC, added carbon fiber around individual blocks, applied heat of 0.5W from back
- temperature profile back to front looks very similar
- temperature profile lateral is different crystal to crystal - change between blocks: min~10, max~11.7degC
- Discussion why there is a change in temperature profile lateral (the outer crystals) from back to front
- There may be gaps between crystals in the model - this would effectively make the inner crystal thermally isolated -- need to check
- Note: important for the experiment is the temperature variation crystal to crystal - don't want different light yield crystal to crystal
- light yield change 2%/degC
- ideally want sub-degree variation
- Database being created of all NPS plots, e.g., CAEN model tests, HV supply tests, etc.
- Actions:
- Check on air gaps in the model
- Thermal analysi of the full (36x31) NPS assembly
PRESHAPING ACTIVITY
- 2-3 people from DSG will participate
- currently have available 4 jigs - will produce 6 more
- ODU tech will help too
- provided 6 jigs and 500 foils
- start with 30-40 foils then quality check
- Action item:
- work our arrangement for pre-shaping activity space at JLab
- Produce additional 6 jigs
- Check in on ODU progress
MECHANICAL
- Work ongoing, e.g., detector lift fixture, cables, etc.
CRYSTALS
- Have been receiving ~40 crystals/month from CRYTUR
- all good quality
- most of them now with the "new" raw material (available from vendor instead of using the raw material from Giessen U.)
NEXT MEETING: THURSDAY 30 SEPTEMBER AT 9AM ET