SciGlass prototype 2022
<-- Back to Beam Tests Main Page
People
- CUA: Tanja Horn (superviser), Yeranuhi Ghandilyan, Joshua Crafts, VSL Team
- JLab: Vladimir Berdnikov, Sasha Somov
- AANL: Hakob Voskanyan, Arthur Mkrtchyan, Hamlet Mkrtchyan, Vardan Tadevosyan, ...
- INFN: Marco Battaglieri, ...
Meetings
Physical characteristics of the glass
Physics
Visual inspection of the SciGlass modules
Dimensions
- 2022 Generation SciGlass 40cm: Dimensions of 9 blocks produced in summer 2022 (CUA-1....CUA-9
Transmission
- 2022 Generation SciGlass 40cm: Comparison of 9 blocks produced in summer 2022
cosmic test
Engineering part and design of the 3x3 prototype (40xm SciGlass 2022)
Hardware
- Filament to print the box for 5x5 (PLA, 1.75mm)
Read out - For the test we will need 25 cables (+3,4 spare) - For the 5x5 prototype we will need to make 25 HV dividers - LEMO bulkhead connectors - HV connectors - HV divider circuit boards + sockets - Cables for dividers - Label Machine - Black RTV silicone - Black type (4.00", 101.60 mm)
Construction of the 3x3prototype (40cm SciGlass 2022)
Installation of the 3x3 prototype (40cm SciGlass 2022) in the beam line (HallD) at Jefferson Lab
Beam alignment and re-alignment
Data from Prototype tests
Detailed List of Activities
Date?? - Visual inspection of the SciGlass "(Josh)"
09/16/2022 - Transmittance measurement (Josh, Yeran)
09/29/2022 - Dimensions measurement (Josh, Yeran)
09/29/2022 - Beam test with 12x1 array in the Hall, (Vlad, Arshak)
10/06/2022 - 12x1 array removing from the hall (Yeran, Arshak)
10/11/2022 - 3x3 prototype cosmic test in clean room, (Yeran, Arshak)
10/13/2022 - 3x3 prototype box assembling (Josh, Yeran)
10/14/2022 - 3x3 prototype installation in the hall and alignment (Yeran, Vlad, Arshak, Sasha)
10/18/2022 - 3x3 prototype re-alignment (5mm), (Yeran, Arshak, Sasha)
10/19/2022 - 3x3 prototype re-re-alignment (5+3mm), (Vlad, Arshak)
10/27/2022 - 3x3 prototype HV base replacement "(Yeran, Arthur, Arshak)" https://userweb.jlab.org/~yeran/SciGlass/3x3-HV.pdf
10/28/2022 - 3x3 prototype central channel's (#5) HV divider/base replacement "(Yeran, Arshak)" https://userweb.jlab.org/~yeran/SciGlass/3x3-HV-updated.pdf
Future Plans
Most probably on Thursday (October 27 2022) will be an access to the Hall-D. We are planning to change the HV dividers (to those with no pre-amplifier) and increase HV (from 1000 V to 1100 V) on the 3x3 prototype in order to improve the photodetection efficiency. Everything is ready to go to the Hall. Since there is no paper-based instruction for all this procedure, I'll try to make one for the future tests. https://userweb.jlab.org/~yeran/SciGlass/Towers+5mm+3mm.pdf