NPS MAGNET UPDATE
- Discussion about yoke
- Designer verified that amount of steel from the pole tip of BNL's Multiparticle Spectrometer is sufficient for the entire NPS magnet including the extra steel required for WACS experiments
- Steel arrived at JLab and is stored in the test lab
- Estimated time until start of construction is ~4 months
- Action item: still need full magnet model - requires support from designer
- Discussion about conductor and coil
- Conductor and suitable power supply (HKS) have been identified, so could start production of coil relatively soon - requires support from designer
- field in gap is good - 5 kG as required, no saturation
- Discussion about fringe fields
- an alternative coil design could reduce fringe fields by factor 4 and also optimize the geometry from the design point of view
- the alternative coil design would use the same conductor, but would go effectively twice around
- Action item: ask for quotation for both coil designs
- Action item: check on other power supplies, e.g., SOS power supply - how close are the parameters?
NPS BACKGROUND STUDIES
- Discussion about the NPS GEANT4 simulation
- Action item: make a comparative study with magnet in vertical and horizontal field configuration and check if there any high dose rates in crystals in the horizontal case
- should change to hydrogen/deuterium target in simulation - assume 10 cm long targets
- do not apply any thresholds in this study
COMPACT PHOTON SOURCE
- Discussion about dump design and radiation control issues, which are a major factor in the design. An important aspect to move forward is to resolve technical issues, e.g.,
- materials needed to construct the dump
- starting from, e.g., the Hall D dump, how could one construct a more compact one that is also servicable
- Discussion about a workshop on the use of an intense photon source and polarized targets
- best time for this seems to be on the scale of 6-9 months - could be adjacent to the next NPS collaboration meeting
- Presentation and discussion about improvement of figure of merit of approved WACS experiment with compact photon source
- taking into account all aspects the improvement is a factor of ~17
- Discussion about impact of heat load in depolarization - how does rotation affect space needed and amount of target material
ITEMS FOR NEXT MEETING:
- Coil quotations (Bogdan)
- Comparative background study (Vardan)
- Other...