General Meeting Summary 10/28/21

From Cuawiki
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

PARTICIPANTS: Aaron, Arshak, Charles, Brad, Hamlet, Paulo, Petr, Steven, Tanja, Vardan, Vladimir, Carlos, Fernando, Rolf, Bogdan, Julie

GROUNDING OF NPS (Fernando)

  • Detector chassis isolated from any detector structure
  • Chassis connected to electronics ground and thick cable that connects to clean ground in hall
  • CAD drawing in progress


HV DIVIDER (Fernando)

  • Optimized design PCB nearly complete
  • Testing the full dynamic range of optimized divider design suggests that need to increase gain
  • also requires higher bandwidth - may need to change chip
  • Communication with Orsay team on grounding connectors
  • CAD drawing with connector position provided - can be considered final
  • Recall two options presented by Orsay team:
  • fixed wire
  • connector

LOW VOLTAGE (Carlos)

  • PCB designed and quotes
  • expect end of year/early January
  • low voltage cables - can be purchased with connector from samtek or flat cable + modify and add connector
  • Action: request quote (Fernando) - Orsay needs to provide cable lengths
  • Timelines:
  • Low voltage cables should be done by beginning January
  • Expect HV Dividers to be in hand end of the year to beginning January


DSG UPDATES (Aaron)

  • Thermal simulations
  • Ambient air temperature determines crystal temperature
  • expected load is 0.5W
  • very stable at lower heat loads - for 0.5W per crystal
  • keeping at 18degC seems a good choice
  • Ambient experimental hall temperature typically 20-21 degC
  • plan to investigate adding cooling flow and also add wrapping material and investigate additional ambient temperatures
  • NPS will have air flow to prevent condensation, but this will be dry air,
  • Reflector shaping - made 110 so far, 16% done
  • ODU has 500 foils - expects to deliver the first 100 pre-shaped foils in first week of November


MECHANICAL (Paulo)

  • much progress with design and procurement of components
  • cabling strategy for roof block finalized - present design focus is on sections near beamline, which will determine remaining cabling strategy


ASSEMBLY PREPARATION DISCUSSION

  • Need dates when people on site
  • first thoughts - end of January/beginning February sounds possible
  • vaccination mandatory to travel to US from November 8th - negative Covid test also still needed
  • Electronics - good progress with electronics components
  • LV PS received and stored
  • Expectation: installation NPS in spring/summer 2023, first NPS run in fall 2023
  • Start thinking about next collaboration meeting


NEXT MEETING: THURSDAY 2 DECEMBER 2021 AT 9AM ET