General Meeting Summary 12/17/20

From Cuawiki
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

PARTCIPANTS: A. Brown, A. Camsonne, B. Wojtsekhowski, B. Sawatzky, C. Munoz-Camacho, C. Yeros, R. Ent, H. Mkrtchyan, P. Medeiros, S. Lassiter, S. Wood, V. Tadevosyan, V. Berdnikov, M. Boer, C. Hyde, H. Voskanyan


FRAME (Carlos)

  • Front face: securing plate for during transportation
  • PCB boards cabling: 29/31 done, should be done this week
  • NPS ready to be shipped - expect shipping in early January
  • Positioning: x-positioning tolerance mm scale from physics (mainly from survey), pointing of crystals to target, long target
  • During crystal stacking PCBs can be inside or outside the box
  • Action:
  • check on access to holes to secure the box to the rails
  • pressure check on frame before any crytal stacking etc. (S. Lassiter)


DSG UPDATES (Aaron)

  • Fabrication of 1100 cables complete!
  • Procurements almost all received
  • Modeling of NPS and development of fault condition flowcharts
  • different zones: electronics zone, crystal zone
  • interlocks on various things to protect the system, e.g. temperature (T>18degC), humidity (>40%)
  • Actions
  • humidity sensor cables access
  • Coolant pressure
  • Working with CAEN on non-functional module replacement


ASSEMBLY SPACE - REFLECTOR AND NPS

  • EEL126 planned for pre-shaping
  • Main assembly should be in ESB, see Brad's drawings for space requirements
  • check in with Walt's team in early January
  • Discussion about strategy for crystal wrapping and installation, e.g. at the same time or wrap crystals and store until installation - continue in more detail at collaboration meeting


COLLABORATION MEETING AGENDA

  • Topics seem complete, need to assign discussion leaders
  • Introduction talk should be no longer than 10 minutes with at least 20 minutes for open discussion


NEXT MEETING: THURSDAY 14 JANUARY AT 9:00AM ET