General Meeting Summary 3/26/20

From Cuawiki
Revision as of 18:40, 26 March 2020 by Hornt (talk | contribs)
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

MAGNET (Charles)

  • Work on To-Do List items, e.g. checking measurement vs. 3D model is ongoing - see NPS To-Do List for a complete listing


MECHANICAL DESIGN (Bogdan, Steven L.)

  • Check and document all kinematics with latest requirements for interferences, e.g. shelf plates on SHMS and new experiment DVCS from Hall A
  • Action Item: collect and send the kinematics information to Steven L. (DVCS: Carlos/Charles, WACS/CPS: Bogdan/David H.)
  • Document time estimate for rotating the magnet, moving the NPS detector and cabling, moving NPS from one side to the other
  • Action Item: develop possible models for cable layout - might need to get in touch with Brad and Jack
  • Corrector magnet fit - Bogdan will work with Paulo on the details


FRAME (Carlos)

  • Magnetic shield tests - note: max field expected is ~200 Gauss longitudinal
  • measurements show that 0.5mm mu-metal works in that range of magnetic fields
  • initial measurements show that PMT signal in magnetic field drops faster than projected by the manufacturer - discussion about possible residual fields, which could cause this effect, also could lead to a transverse field.
  • Assembly of the frame started and was well underway until the lab shutdown on March 16 - anticipated delay roughly equal to length of closure
  • Crystals and LED connectors sent from JLab arrived in France - should be delivered at Orsay end of the week


CRYSTALS (Vladimir, Tanja)

  • Crytur has been sending more crystals (50+10) over the last weeks - production seems to continue
  • Action Item: Check with CRYTUR if they can expedite outstanding crystal delivery for 250 crystals purchased recently and possible early FY21 procurement for 200 more
  • SICCAS shipped a number of crystals - arrival at JLab not yet known


HV DIVIDERS (Fernando, Alex S.)

  • New HV dividers with additional amplification that improves linearity have been tested in Hall D and seem to perform well
  • Action Items:
  • Collect results from Hall D and projected intensity of signals and performance for Hall A/C conditions
  • Collect all information on Hall A/C projections, e.g. from Ho-San's simulations for discussion at next meeting


DISCUSSION (All)

  • NPS global delay likely a few months - will evaluate when Labs/Universities return to normal operations


NEXT MEETING: THURSDAY 16 APRIL AT 9:00AM (ET)