General Meeting Summary 3/7/19

From Cuawiki
Revision as of 08:42, 19 March 2019 by Hornt (talk | contribs) (Created page with "MAGNET (Charles, Bogdan) * Safety and Operations documents ::* OSP for mapping is being prepared - expected to be complete in week 3/11 ::* More detailed documents needed for...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

MAGNET (Charles, Bogdan)

  • Safety and Operations documents
  • OSP for mapping is being prepared - expected to be complete in week 3/11
  • More detailed documents needed for ERR
  • Details of mapping plan for ERR
  • Planning to bring mapper to JLab in week 3/11
  • Fringe fields
  • Additional calculations made for downstream of magnet with passive shielding - sent this information to Jay Benesch
  • Action item: redo calculations of front of HMS (snout) for ERR - this is relevant for the optics
  • Paulo redid distances
  • need set of kinematic positions
  • Action item: determine sensitivity of experiments to up/down asymmetry due to magnetic field
  • magnet horizontal field changes up/down position of detector - for measurements only matters if sensitive to up/down asymmetry
  • DVCS measures up/down - need to think about and have answer for ERR
  • Is the power supply reversible? - need to include in ERR


FRAME AND SIMULATIONS (Carlos, Ho San)

  • Working on full prototype for tests of movable boards for PMT access
  • Deciding on cable lengths and work distribution
  • clarifying quotes and prices, e.g. labor and part per cable
  • Testing fibers


HV DIVIDERS (Vladimir, Alex S., Fernando)

  • Discussion of recent ComCal/NPS prototype results
  • Best solutions for NPS HV dividers seems to either bypass amplifier or to reduce the amplification - both are practically easy to do
  • slight preference to bypass the amplifier
  • Planned tests with sample dividers with bypassed amplifier and reduced amplification
  • test with beam in Hall D
  • test bench either after or instead of beam tests - expect to put all together in lab in 2-3 weeks
  • A few notes on PMT, divider, and fADC
  • R4125 is rated for 1500 V operating voltage, maximum anode current is 100 uA
  • fADC dynamic range for earlier 3x3 prototype tests was 1 V
  • ComCal/NPS prototype has different crystals than the 3x3 prototype


CRYSTALS (Vladimir, Tanja)

  • Received 160 replacement crystals from SICCAS - inspection ongoing
  • In contact with Crytur about procurement of additional crystals


ERR PREPARATION

  • Created Wiki page NPS ERR for people to start filling in


NEXT MEETING: THURSDAY 21 MARCH at 9:00 AM (ET)