General Meeting Summary 4/16/20

From Cuawiki
Revision as of 14:07, 17 April 2020 by Hornt (talk | contribs) (Created page with "PARTICIPANTS: V. Berdnikov, A. Camsonne, C. Munoz-Camacho, R. Ent, M. Fowler, T. Horn, C. Hyde, S. Lassiter, P. Medeiros, H. Mkrtchyan, J. Murphy, J. Roche, V. Tadevosyan, B....")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

PARTICIPANTS: V. Berdnikov, A. Camsonne, C. Munoz-Camacho, R. Ent, M. Fowler, T. Horn, C. Hyde, S. Lassiter, P. Medeiros, H. Mkrtchyan, J. Murphy, J. Roche, V. Tadevosyan, B. Wojtsekhowski

MAGNET AND DESIGN (Charles, Paulo, Steven, Mike)

  • Analysis of magnet fringe field data and comparison to calculation is ongoing
  • The Hall A/C engineering/design team is working on NPS cable layout
  • Two main routing options, one more direct but also makes cables longer - seems fine from NPS point of view, but need to check with Hall C
  • Also need to take into account CPS in overall cable layout
  • Action items:
  • Send updated DVCS kinematics table with settings moved to Hall C from Hall A to Steven L.
  • Check with Brad S. on cable routing, patch panel, etc.
  • Include CPS in overall cable layout


FRAME (Carlos)

  • Construction started, but on hold until end of lockdown - currently expect re-opening after May 11
  • Crystals and LED connectors arrived in Orsay
  • Cabling of LED connectors is ongoing
  • Action item: check on cable making effort at JLab


CRYSTALS (Vladimir, Tanja)

  • Had email communication with Crytur. Vendor is working on a proposal for crystal delivery for rest of FY20 and FY21 - expect update after 4/17
  • A few boxes of Crytur crystals that arrived last month await to be inspected. Furthermore, the expected SICCAS crystal arrived (60 of those to NPS) and await inspection
  • SICCAS crystals were preselected in Shanghai by a FCAL collaborator from Wuhan U. - 13% of all inspected crystals were rejected based on simple visual inspection
  • Action items:
  • check on options for Crytur to send ~70-100 crystals to JLab on 30 August. These would arrive in multiple boxes with different invoices due to issues with the carrier on vendor's side.
  • check on options for both vendors to keep producing and sending crystals - options for storage at JLab


HV DIVIDERS (Vladimir, Tanja)