General Meeting Summary 6/30/22

From Cuawiki
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

PARTICIPANTS: Aaron Brown, Alexandre Camsonne, Fernando Barbosa, Bogdan Wojsekhowski, Brad Sawatzky, Carlos Munoz-Camacho, Deb Biswas, Erik Wrightson, Hamlet Mkrtchyan, Julie Roche, Steven Lassiter, Marie Boer, Mark Jones, Paul King, Abishek Karki, Paulo Medeiros, Vardan Tadevosyan, Vladimir Berdnikov, Tanja Horn, Pramita Tiwari


ASSEMBLY UPDATES

  • Crystal stacking
  • viewing photos of NPS during assembly - one taken at same angle as the mechanical drawing
  • Cabling
  • presently 4 columns are fully cabled and PCBs installed
  • time for installation: 2 columns/day - 2 people can work, need to take shifts
  • cabling the remaining 26 columns would take 3 weeks total
  • cosmic paddles are installed and connectors - HV and signal cables need to be connected to the paddles
  • Ongoing:
  • cabling on top part (PS, DAQ, LED controls, LV)
  • connect HV and signal cables and PS for fans
  • DAQ/Cables/Infrastructure - 80% moved into EEL-108 and cables being bundled
  • The team: Hamlet, Vardan, Pramita, Erik
  • God progress - to date 200 cables bundles
  • Discussion about moving NPS equipment out of the HD cleanroom area with target date July 6th
  • NPS detector stays in its area
  • crates can be disposed of
  • HV cables complete in EEL126 - ready to go
  • LV cables - being put together (Fernando and team)


ASSEMBLY PLANNING

  • Finishing the cabling of 26 remaining columns
  • Orsay team could come to finish up cabling
  • in preparation need to do PMT assembly
  • Preparation of PMTs
  • put PMT together with HV divider and put sticker on it
  • Orsay team can then do the more detailed assembly
  • plan to complete PMT preparation by end of August
  • Maintenance of detector
  • anyone can participate and be training in the assembly of columns
  • contact Carlos to schedule
  • Turning on the HV and start tests
  • plan to hook up the 4 columns into the DAQ before the end of July
  • PMT checkout with scope
  • plug into DAQ
  • check out system with DAQ
  • run and read all instrument analysis and controls (chiller, temp, etc.)
  • Brad should be there for initial HV turning on
  • Check of HV cables
  • continuity check - was done for inside cables
  • recommendation: do visual inspection for outside cables
  • have some spare cables as needed


DSG UPDATES (Aaron)

  • EPICS PHOEBUS screen development - monitoring and control screens for both chiller and thermal readback
  • can be rolled out as soon as next week for checking out the readbacks before turning on the HV
  • ready to run on Linux - software environment should be compatible
  • System to run on is cdaql3 - start staging software there
  • Configuration file control
  • Ansys thermal analysis
  • investigate how heat propagates along crystals
  • Cables for scintillator paddles: all parts on site except pins; once these arrive assembly can happen
  • HV crates
  • one is still with the DSG (HallC-1); located in cleanroom in front of EEL-108
  • LED control GUI
  • setup is done, need to do programming
  • Action Items:
  • install HV controls and GUI on cdaql3 and test
  • LED control GUI programming - set up meeting with Brad
  • LED ribbon cable connectors - crimp on connectors - contact Amrit about the task (Brad)


MECHANICAL UPDATES (Paulo)

  • New beamline procurement
  • proceed with small angle beamline
  • wait with larger angle beamline procurement for simulation results


DAQ/ELECTRONICS/SOFTWARE

  • Critical path: event unblocking - ongoing discussions with David H. about possible options
  • For detector checkout all is in end
  • modified firmware etc. will be checked
  • need to go through the full chain
  • Grounding and tests of ground
  • ground connector on HV divider
  • ground on frame is available but not planning to connect it - are there any tests that could be done to verify that it is not needed before columns cabling is finished?
  • start with a clean setup for baseline
  • next check noise pickup, e.g., plug in a number of noise devices and see if pickup exists

NEXT MEETING: THURSDAY 21 JULY 2022 AT 9:00AM ET