MAGNET UPDATES

  • Yoke delayed until end of September
  • Main coil delayed until end of November
  • company miscalculated amount of copper needed and takes a few months to obtain
  • in general, company does good work
  • Test lab configuration for magnet assembly and testing ongoing
  • due to delays of magnet component shipping magnet tests will be delayed past December


CRYSTALS AND PMTS

  • Received 100 PMTs from Hamamatsu
  • diameter < 19.2 mm according to specifications
  • Crystal shipment delayed
  • Check with company at beginning of September for expected delivery dates
  • Crystal Q&A documentation discussion
  • need to make sure that there is unique labeling and data sheet for each crystal
  • create an NPS database that includes crystal info, but also info on PMTs, frame etc.
  • indicate what tests have been done by Giessen and/or CMS - use this information to determine if crystal good with respect to these two
  • Discussion about resource optimization
  • split measurements between institutions
  • measure only subsets
  • external resources to supplement resources at CUA/IPNO - Glasgow may be able to help with some tests
  • Discussion about crystal measurement procedures
  • make a detailed list of procedures to follow to minimize damage to crystals


FRAME UPDATES

  • Designer will be available full time at IPNO in September
  • Currently working on curing system optimization and finalization
  • Still need some final design optimizations from JLab designer, e.g. interference in detector box


DISCUSSION ABOUT 2017 ACTION ITEM LIST

  • Magnet mapping - discussions and write-up of plan ongoing
  • plan to map along beam line for 2-3 positions
  • primary tools: hall probe and oscilloscope
  • may be able to do some tests with yoke and corrector coil before main coil arrives


  • Platform - JLab designer
  • Readout
  • Crystals - large part of planning work completed, some still ongoing, waiting for crystals
  • PMT and HV bases - concept finalized, procurement ongoing


DAQ AND READOUT

..