Meeting 27 March 2020

From Cuawiki
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

DISCUSSION TOPICS

  • Magnet and shielding
  • Hall D updates
  • Other


ACTION ITEMS

  • Analyze recent radiation simulation results
  • Make an updated Hall A/C CPS sketch (new overall dimensions, weight) for Steve L. and team to check in the model. Make sure all CPS kinematics are available to the engineers/designers. Plan to discuss with the engineering team in April 17 meeting.
  • Get suggested Hall D CPS configurations (Sean)


SUMMARY NOTES

  • Radiation simulations (Gabriel)
  • Pb configuration works in the backward region (<0cm)
  • Tungsten seems the best option for the forward region, but some more tuning may be needed, e.g. more W laterally out to 70cm
  • Tungsten may be down to ~1m3
  • Was there a low energy cut applied? What was it?


  • Magnet and CPS design (Bogdan, Thia)
  • Keeping all components on the pivot may be difficult - possible options were discussed with the engineering team. Should check in where they are.
  • About 100 tons of lead are available from SLAC. Process has started to ship ~80 tons of lead to JLab. Discussion about storage ongoing with RADCon
  • Hall D CPS
  • Tagger area in Hall D: should be fine to move permanent magnet downstream and put CPS in that position
  • Weight up to ~150 tons (few square meters) should be fine
  • Need suggested configurations from Sean
  • TCS: work on checking the impact of magnetic field on low energy (~100 MeV) particles is ongoing


NEXT MEETING: FRIDAY 17 APRIL AT 11:00AM (ET)