Line 4: Line 4:
  
 
* Shielding and magnet model - check of numbers of modules and analysis of radiation hard coil model
 
* Shielding and magnet model - check of numbers of modules and analysis of radiation hard coil model
 +
::* [https://wiki.jlab.org/cuawiki/images/8/84/CPS_Initial_Design_Model_10_29_20.pptx CPS Design Model Update]
  
 
* Hall A/C model and design/implementation - thermal model development etc.
 
* Hall A/C model and design/implementation - thermal model development etc.
Line 10: Line 11:
  
 
* Other
 
* Other
 +
 +
 +
PARTICIPANTS: Amy Comer, Rolf Ent, Hamlet Mkrtchyan, Hovanes Egiyan, Igor Strakovsky, Josh Crafts, Steven Lassiter, Vardan Tadevosyan, Vladimir Berdnikov, Tanja Horn, Marie Boer
 +
 +
 +
'''SUMMARY NOTES'''
 +
 +
'''SIMULATIONS POWER DEPOSITION''' (Gabriel)
 +
 +
* Apply two-Gaussian to all panels
 +
 +
* '''Action''': make a paramaterization in z (with some segmentation in x) - the quality of the tails in the fit may not be so important
 +
::* Also investigate if possible to use lookup tables
 +
 +
 +
'''SHIELDING MODELING''' (Josh)
 +
 +
* Investigation of number of blocks - issue found and resolved
 +
::* Pb blocks 1867, W blocks ~2200
 +
::* expect Pb weight 28 tons, W weight ~20 tons
 +
 +
* Surface quality: if block sizes small should have small tolerances - sensitivity in stacking
 +
::* alternative: large W block, e.g. 10 tons or so like for spectrometer collimator?
 +
::* '''Action''': status of CUA tests with W blocks
 +
 +
* '''Action''': continue shielding model work
 +
 +
 +
'''DESIGN/IMPLEMENTATION - THERMAL CALCULATIONS''' (Amy)
 +
 +
* CPS: length: 20cm, width starts at a few mmm, depth
 +
 +
* '''Action''': investigate why temperature output high, e.g. heat source input too large (should be total 30kW for entire system), assumptions on cooling pipes, etc.
 +
 +
 +
'''HALLD UPDATES - RADIATION SIMULATIONS''' (Hovanes)
 +
 +
* Investigating energy deposition - cooling system
 +
::* Working on Fluka simulations, modify gap and beam size and investigate energy deposition
 +
::* Working on GEANT4 simulations - Jim Ritman team
 +
::* Working with JLab RadCon team on another code - for beryllium source and CPS
 +
 +
 +
'''NEXT MEETING: FRIDAY 4 DECEMBER AT 8:00AM (ET)'''

Latest revision as of 23:46, 1 November 2020

DISCUSSION ITEMS

  • Simulations - parameterization of power deposition
  • Shielding and magnet model - check of numbers of modules and analysis of radiation hard coil model
  • Hall A/C model and design/implementation - thermal model development etc.
  • Hall D design and radiation simulations
  • Other


PARTICIPANTS: Amy Comer, Rolf Ent, Hamlet Mkrtchyan, Hovanes Egiyan, Igor Strakovsky, Josh Crafts, Steven Lassiter, Vardan Tadevosyan, Vladimir Berdnikov, Tanja Horn, Marie Boer


SUMMARY NOTES

SIMULATIONS POWER DEPOSITION (Gabriel)

  • Apply two-Gaussian to all panels
  • Action: make a paramaterization in z (with some segmentation in x) - the quality of the tails in the fit may not be so important
  • Also investigate if possible to use lookup tables


SHIELDING MODELING (Josh)

  • Investigation of number of blocks - issue found and resolved
  • Pb blocks 1867, W blocks ~2200
  • expect Pb weight 28 tons, W weight ~20 tons
  • Surface quality: if block sizes small should have small tolerances - sensitivity in stacking
  • alternative: large W block, e.g. 10 tons or so like for spectrometer collimator?
  • Action: status of CUA tests with W blocks
  • Action: continue shielding model work


DESIGN/IMPLEMENTATION - THERMAL CALCULATIONS (Amy)

  • CPS: length: 20cm, width starts at a few mmm, depth
  • Action: investigate why temperature output high, e.g. heat source input too large (should be total 30kW for entire system), assumptions on cooling pipes, etc.


HALLD UPDATES - RADIATION SIMULATIONS (Hovanes)

  • Investigating energy deposition - cooling system
  • Working on Fluka simulations, modify gap and beam size and investigate energy deposition
  • Working on GEANT4 simulations - Jim Ritman team
  • Working with JLab RadCon team on another code - for beryllium source and CPS


NEXT MEETING: FRIDAY 4 DECEMBER AT 8:00AM (ET)