'''Timeline'''
 
'''Timeline'''
  
* '''February''' - pre-installation tasks (see: link)
+
* '''February''' - pre-installation tasks (see: [https://docs.google.com/spreadsheets/d/1zvJLaskBxPr61IM0zkmumfyurz3CvkXzL0oiQSEl2Ss/edit#gid=1452894085 link])
 
::* complete calorimeter trigger
 
::* complete calorimeter trigger
 
::* upgrade HMS DAQ
 
::* upgrade HMS DAQ
 
::* calorimeter tests
 
::* calorimeter tests
  
* '''March''' - pre-installation tasks (see: link)
+
* '''March''' - pre-installation tasks (see: [https://docs.google.com/spreadsheets/d/1zvJLaskBxPr61IM0zkmumfyurz3CvkXzL0oiQSEl2Ss/edit#gid=1452894085 link])
 
::* complete calorimeter trigger
 
::* complete calorimeter trigger
 
::* upgrade HMS DAQ
 
::* upgrade HMS DAQ

Revision as of 15:52, 7 February 2023

Timeline

  • February - pre-installation tasks (see: link)
  • complete calorimeter trigger
  • upgrade HMS DAQ
  • calorimeter tests
  • March - pre-installation tasks (see: link)
  • complete calorimeter trigger
  • upgrade HMS DAQ
  • calorimeter tests
  • April 15 - April 30: start disconnecting cables from NPS in EEL108
  • disconnect cables
  • bundle cables and prepare for transport
  • May 3rd: NPS detector moves to Hall C
  • May 15 - May 30: connect cables to the NPS detector
  • June 1 - July 14: NPS detector checkout in Hall C
  • July 17: NPS Experiments Phase 1 start