Special Meeting LV Cable Strategy Summary 9/22/21

From Cuawiki
Revision as of 22:06, 22 September 2021 by Hornt (talk | contribs)
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

PARTICIPANTS: Bogdan, Carlos, Emmanuel, Thi, Vladimir, Tanja

FERNANDO'S NOTES ON LV POWER DISTRIBUTION

PRACTICAL IMPLEMENTATION CABLING

  • Found suitable connector with 6 pins
  • HV
  • Ground
  • Signal
  • Problem: Flat cables interfere with HV cables --> shift connectors
  • Horizontal back chaining with shifted connectors
  • less work than connector on side, but more risky during assembly/disassembly
  • Three issues - most problematic: interference with HV cables
  • Discussion: can one cut connector
  • need only three pins, so maybe can cut to resolve interference with HV cables
  • Alternative: connector on the side
  • less risky
  • requires more work - have to make additional cables etc.
  • requires fabrication of 1000 flat cables and ~30 other cables - time estimate: ~3 weeks
  • PCB design time estimate: ~3 months (expect ready early 2022)
  • Action item:
  • write to DSG and ask if available to take on cable fabrication task
  • provide information on connector and placement to Fernando
  • Discussion: additional grounding
  • action item: investigate how this may be realized


NEXT MEETING: NPS MEETING ON THURSDAY 30 SEPTEMBER AT 9AM ET