Difference between revisions of "HPS 2016 Trigger Commissioning"
Jump to navigation
Jump to search
Line 5: | Line 5: | ||
#* 30 minutes at any current | #* 30 minutes at any current | ||
− | == Phase 1: Tuning == | + | == Phase 1: Preliminary Tuning == |
# ECal Pedestal Runs | # ECal Pedestal Runs | ||
#* About 10 minutes at each beam current: | #* About 10 minutes at each beam current: | ||
Line 25: | Line 25: | ||
− | == Phase 2: Tuning == | + | == Phase 2: Final Tuning == |
coming soon | coming soon |
Revision as of 18:21, 4 February 2016
Phase 0: Diagnostics
- Aprime Runs with Singles&Pairs
- trigger file: HPS/Run2016/v0.trg
- 30 minutes at any current
Phase 1: Preliminary Tuning
- ECal Pedestal Runs
- About 10 minutes at each beam current:
- 25 nA (or lower)
- 100 nA
- 200 nA
- About 10 minutes at each beam current:
- 20 kHz Pulser Runs
- trigger file: HPS/Run2016/20kHz.trg
- At least 100 Million events (~1 hour) at each beam current:
- 25 nA (or lower)
- 100 nA
- 200 nA
Ideally the pedestal runs should be done first so that they can be used
to update the pedestals used for the 20 kHz Pulser runs. This requires
an ECal expert available, and to then update the trigger files for the
subsequent Pulser runs. If this is not the case, the Pulser runs can be
done first with the preconfigured pedestals.
Phase 2: Final Tuning
coming soon