− | <font size="3">Upstream beamline commissioning and beam tune using the tagger dump (beam will not go through the Hall). The goal is to get CW stable beam to | + | <font size="3">Upstream beamline commissioning and beam tune using the tagger dump (beam will not go through the Hall). The goal is to get CW stable beam to the Hall-B tagger dump, on 2C24 harp (tagger harp) achieve beam parameters routinely used in Hall-B 6-GeV era <font color=red> X/Y width ~150 micron, and S/N on halo counters from harp wire >10E4</font>. </font> |
* Follow procedures in the "[https://wiki.jlab.org/hps-run/images/0/0d/HPS_beamline_commissioning.pdf Beamline commissioning plan]". Tuning beam to tagger dump is covered under item (A). Depending on the machine state, items (A.7) and (A.8) may not be feasible to complete at this time. | * Follow procedures in the "[https://wiki.jlab.org/hps-run/images/0/0d/HPS_beamline_commissioning.pdf Beamline commissioning plan]". Tuning beam to tagger dump is covered under item (A). Depending on the machine state, items (A.7) and (A.8) may not be feasible to complete at this time. | ||
− | * | + | * First establish 6-GeV era quality beam <font color=red> X/Y width ~150 micron, and S/N on halo counters from harp wire >10E4</font> on tagger (2C24) harp. |
+ | * Then, using optics setting used in A. Freyberger's "[http://www.jlab.org/Hall-B/run-web/hps/manuals/HPS_Beamline.pdf]" simulations, achieve needed beam parameters at 2C24/tagger harp to deliver HPS requested beam ("pancake") on target in downstream alcove. | ||
{| | {| |
Revision as of 11:57, 9 November 2014
[edit]
RC: Stepan StepanyanPDL: Harut AvagyanEvery Shift:
Every Run:
|
Run Plan: Nov. 9 - Nov. 10Upstream beamline commissioning and beam tune using the tagger dump (beam will not go through the Hall). The goal is to get CW stable beam to the Hall-B tagger dump, on 2C24 harp (tagger harp) achieve beam parameters routinely used in Hall-B 6-GeV era X/Y width ~150 micron, and S/N on halo counters from harp wire >10E4.
|
|
|
|