== Run Plan: Nov. 9 - Nov. 10 ==
 
== Run Plan: Nov. 9 - Nov. 10 ==
<font size="3">Upstream beamline commissioning and beam tune using the tagger dump (beam will not go through the Hall). The goal is to get CW stable beam to the Hall-B tagger dump, on 2C24 harp (tagger harp)  achieve beam parameters routinely used in Hall-B 6-GeV era <font color=red> X/Y width ~150 micron, and S/N on halo counters from harp wire >10E4</font>. </font>
+
<font size="3">Upstream beamline commissioning and beam tune using the tagger dump (beam will not go through the Hall). The goal is to get CW stable beam to the Hall-B tagger dump, on 2C24 harp (tagger harp)  achieve beam parameters routinely delivered to Hall-B in "[http://clasweb.jlab.org/clasonline/servlet/newloginfo?action=logentry&entryId=41734 6-GeV era]" <font color=red> X/Y width ~150 micron, and S/N on halo counters from harp wire >10E4</font>. </font>
  
 
* Follow procedures in the "[https://wiki.jlab.org/hps-run/images/0/0d/HPS_beamline_commissioning.pdf Beamline commissioning plan]". Tuning beam to tagger dump is covered under item (A). Depending on the machine state, items (A.7) and (A.8) may not be feasible to complete at this time.
 
* Follow procedures in the "[https://wiki.jlab.org/hps-run/images/0/0d/HPS_beamline_commissioning.pdf Beamline commissioning plan]". Tuning beam to tagger dump is covered under item (A). Depending on the machine state, items (A.7) and (A.8) may not be feasible to complete at this time.