== Run Plan: Nov. 9 - Nov. 10 ==
 
== Run Plan: Nov. 9 - Nov. 10 ==
<font size="3">Upstream beamline commissioning and beam tune using the tagger dump (beam will not go through the Hall). The goal is to get CW stable beam to the Hall-B tagger dump, on 2C24 harp (tagger harp)  achieve beam parameters routinely used in Hall-B 6-GeV era <font color=red> X/Y width ~150 micron, and S/N on halo counters from harp wire >10E4</font>. </font>
+
<font size="3">Upstream beamline commissioning and beam tune using the tagger dump (beam will not go through the Hall). The goal is to get CW stable beam to the Hall-B tagger dump, on 2C24 harp (tagger harp)  achieve beam parameters routinely delivered to Hall-B in "[http://clasweb.jlab.org/clasonline/servlet/newloginfo?action=logentry&entryId=41734 6-GeV era]" <font color=red> X/Y width ~150 micron, and S/N on halo counters from harp wire >10E4</font>. </font>
  
 
* Follow procedures in the "[https://wiki.jlab.org/hps-run/images/0/0d/HPS_beamline_commissioning.pdf Beamline commissioning plan]". Tuning beam to tagger dump is covered under item (A). Depending on the machine state, items (A.7) and (A.8) may not be feasible to complete at this time.
 
* Follow procedures in the "[https://wiki.jlab.org/hps-run/images/0/0d/HPS_beamline_commissioning.pdf Beamline commissioning plan]". Tuning beam to tagger dump is covered under item (A). Depending on the machine state, items (A.7) and (A.8) may not be feasible to complete at this time.

Revision as of 12:15, 9 November 2014

[edit]

RC: Stepan Stepanyan

PDL: Harut Avagyan

Every Shift:

  1. Follow run plan as outlined by RC
  2. Keep shift summery up-to-date in HBLOG
  3. Document any beam condition change and send scaler GUIs to HBLOG
  4. Continuously check quality of data

Every Run:

  1. a
  2. b
  3. c
  4. d


MCC Daily Meetings


Run Plan: Nov. 9 - Nov. 10

Upstream beamline commissioning and beam tune using the tagger dump (beam will not go through the Hall). The goal is to get CW stable beam to the Hall-B tagger dump, on 2C24 harp (tagger harp) achieve beam parameters routinely delivered to Hall-B in "6-GeV era" X/Y width ~150 micron, and S/N on halo counters from harp wire >10E4.

  • Follow procedures in the "Beamline commissioning plan". Tuning beam to tagger dump is covered under item (A). Depending on the machine state, items (A.7) and (A.8) may not be feasible to complete at this time.
  • First establish 6-GeV era quality beam X/Y width ~150 micron, and S/N on halo counters from harp wire >10E4 on tagger (2C24) harp.
  • Then, using optics setting used in A. Freyberger's "[1]" simulations, achieve needed beam parameters at 2C24/tagger harp to deliver HPS requested beam ("pancake") on target in downstream alcove.
    • In order to do above program, when CW beam is established, Hall-B beam halo counters and harps (2C21 and 2C24 or tagger) must be calibrated first. So it may take multiple harp scans to set harp motion limits and halo counter PMT gains. With any issue contact beam line expert of RC.
Beam
Energy ~2.0 GeV
Current < 200.0 nA CW
Position
X Y
~0 mm ~0 mm
Profile
X Y
< 0.3 mm < 0.3 mm
Target
#1 0 mm
Magnets
PS Current 0 A
Chicane Dipole #1 0 A
Chicane Dipole #2 0 A
DAQ
Configuration ___________________
Configuration file
Prescales
Thresholds
Events Per Run
Dead Time



AccumulatedCharge.png


Run Coordinator
DATE NAME
DATE NAME
DATE NAME
DATE NAME
Physics Division Liaison
DATE NAME
DATE NAME
DATE NAME
DATE NAME