Difference between revisions of "The HPS Run Wiki"
Jump to navigation
Jump to search
Line 95: | Line 95: | ||
== Run Plan: Nov. 9 - Nov. 10 == | == Run Plan: Nov. 9 - Nov. 10 == | ||
− | <font size= | + | '''<font size=3>Upstream beamline commissioning and beam tune using the tagger dump (beam will not go through the Hall). The goal is to get CW stable beam to the Hall-B tagger dump, on 2C24 harp (tagger harp) achieve beam parameters routinely delivered to Hall-B in [http://clasweb.jlab.org/clasonline/servlet/newloginfo?action=logentry&entryId=41734 6-GeV era] <font color=red> X/Y width ~<150 micron, and S/N on halo counters from harp wire >10E4</font>. </font>''' |
* Follow procedures in the "[https://wiki.jlab.org/hps-run/images/0/0d/HPS_beamline_commissioning.pdf Beamline commissioning plan]". Tuning beam to tagger dump is covered under item (A). Depending on the machine state, items (A.7) and (A.8) may not be feasible to complete at this time. | * Follow procedures in the "[https://wiki.jlab.org/hps-run/images/0/0d/HPS_beamline_commissioning.pdf Beamline commissioning plan]". Tuning beam to tagger dump is covered under item (A). Depending on the machine state, items (A.7) and (A.8) may not be feasible to complete at this time. |
Revision as of 15:26, 9 November 2014
[edit]
RC: Stepan StepanyanPDL: Harut AvagyanEvery Shift:
Every Run:
|
Run Plan: Nov. 9 - Nov. 10Upstream beamline commissioning and beam tune using the tagger dump (beam will not go through the Hall). The goal is to get CW stable beam to the Hall-B tagger dump, on 2C24 harp (tagger harp) achieve beam parameters routinely delivered to Hall-B in 6-GeV era X/Y width ~<150 micron, and S/N on halo counters from harp wire >10E4.
|
|
|
|