* Establish CW 1 pass beam to the Hall-B dump, including checkout of all new beamline components, BPMs, quads, correctors, and harps. | * Establish CW 1 pass beam to the Hall-B dump, including checkout of all new beamline components, BPMs, quads, correctors, and harps. | ||
− | * Work with MCC crew to establish small size stable beam at the alcove harp - beam parameters | + | * Work with MCC crew to establish small size stable beam at the alcove harp - beam parameters sig X ~ 150 micron, sig Y ~50 micron, with low noise in the downstream halo counters and ecal. |
* Perform harp scans using 2H02 harp. Optimize halo counter voltages as needed. | * Perform harp scans using 2H02 harp. Optimize halo counter voltages as needed. | ||
* Once established, commission the chicane magnet, including a study of noise rates (halo counters + ecal) vs B field. (We may need to run slightly lower than nominal B for our given beam energy to afford adequate clearance to the 3 inch beam pipe connected to the new target assembly.The beam pipe must accommodate both straight through and Frascati bent beams.) | * Once established, commission the chicane magnet, including a study of noise rates (halo counters + ecal) vs B field. (We may need to run slightly lower than nominal B for our given beam energy to afford adequate clearance to the 3 inch beam pipe connected to the new target assembly.The beam pipe must accommodate both straight through and Frascati bent beams.) |
Revision as of 19:46, 6 December 2014
[edit]
RC: John Jaros
PDL: Harut AvagyanEvery Shift:
Every Run:
|
Run Plan: Dec. 7 - Dec. 9Beamline commissioning studies using the Hall B dump, followed by studies of the ECal and Trigger. The goal is to get usable CW beam to the Hall-B dump, set up the chicane, and begin to study beam backgrounds and trigger rates.
|
|
|
|
Webcams only accessible inside Hall gateway. |