== Run Plan: Dec. 7 - Dec. 9 ==
+
== Run Plan: Dec. 8 - Dec. 10 ==
 
'''<font size=3> Beamline commissioning studies using the Hall B dump, followed by studies of the ECal and Trigger. The goal is to get usable CW beam to the Hall-B dump, set up the chicane, and begin to study beam backgrounds and trigger rates.  </font>'''
 
'''<font size=3> Beamline commissioning studies using the Hall B dump, followed by studies of the ECal and Trigger. The goal is to get usable CW beam to the Hall-B dump, set up the chicane, and begin to study beam backgrounds and trigger rates.  </font>'''
  
* Establish CW 1 pass beam to the Hall-B  dump, including checkout of all new beamline components, BPMs, quads, correctors, and harps.
+
* Re-establish CW 1 pass beam to the Hall-B  dump, setting beam to specified settings at the dump screen  and the 2H02 harp. Chicane off. 5 nA.
* Work with MCC crew to establish small size stable beam at the alcove harp - beam parameters sig X ~ 150 micron, sig Y ~50 micron, with low noise in the downstream halo counters and ecal.  
+
* Study the dependence of halo counter rates on beam position. Vary x and y of beam by +/- 7.5 mm, with beams parallel to specified settings above.
* Perform harp scans using 2H02 harp. Optimize halo counter voltages as needed.
+
Record scaler rates, BPMs, 2H02 harp, and beam location on dump screen. Choose nominal position close to rate minimum, at old nominal, if possible.
* Once good beam is established, commission the chicane magnet, including a study of noise rates (halo counters + ecal) vs B field. (We may need to run slightly lower than nominal B for our given beam energy to afford adequate clearance to the 3 inch beam pipe connected to the new target assembly.The beam pipe must accommodate both straight through and Frascati bent beams.)
+
* With beam at nominal, set up chicane to specified currents for the -7% field point. Instructions provided in Counting House. Verify harp scan and record
* Commission the HPS target, including measuring noise rates in the Ecal and halo counters vs beam current.
+
location on dump screen. Tweak Frascati current if necessary, and record. Record scaler rates.
 +
* Ditto for -9% beam position.  
 +
* If little change in scaler rates, use -7% setting as chicane standard. If large improvement in scaler rates in going to -9%, try -11%.
 +
* Select standard chicane settings.
 +
* Commission the HPS target, including measuring noise rates in the Ecal and halo counters vs beam current. Call Stepan before first use of target.
 +
* With 1.5 um Pt target, measure scalers and Ecal occ vs beam current.Record Ecal Scalers and scalaer display for each beam current.  
 
* If time allows, begin commissioning the Ecal and trigger with beam on target and data taking.   
 
* If time allows, begin commissioning the Ecal and trigger with beam on target and data taking.   
 
** See <b>[[Media:dec4_beamline_commissioning.pdf|Full PDF, Click Here]]</b>
 
** See <b>[[Media:dec4_beamline_commissioning.pdf|Full PDF, Click Here]]</b>
** With any issue, contact Beamline Expert or RC.</font>
+
** With any issue, contact Beamline Expert, Ecal Expert, DAQ Expert or RC.</font>
  
 
{|
 
{|